## EPA No Action Assurance Letter 

- Issued on November 21, 2024. Extension March-2025 

- Allows ACIs with capacity greater than 35 tons per day to operate in North Carolina without first obtaining a Title V Permit through September 1, 2025 provided that: 

   - The owner/operator notifies the EPA Region 4 (see below for notification contact) prior to initiation of the use of a new ACI subject to the Title V permitting under CISWI 

   - • Owners/operators comply with all other applicable CISWI requirements, including opacity limits, monitoring, testing, and recordkeeping and reporting. 

   - • Owners/operators comply with all conditions imposed by State or local authorities on these emergency operations.