SUBMITTER: Jessica Trotman, Assistant Town  MEETING DATE: June 9, 2025<br>Manager<br>AGENDA SECTION: New Business DEPARTMENT: Administration<br>TITLE OF ITEM: Consideration of Professional Engineering Services Agreement with<br>McAdams for the Hilltop Road Stabilization Project<br>SUGGESTED MOTION(S):<br>To approve the contract as presented.<br>**----- End of picture text -----**<br>


## **SUMMARY:** 

As a result of severe flooding during Tropical Storm Helene, a landslide occurred on Hilltop Road approximately 1,600 feet from its intersection with Fairway Drive. The event removed roughly half the roadway and rendered the remaining portion unstable. Emergency stabilization is necessary to prevent further erosion, protect adjacent property, and prepare the site for future roadway reconstruction. 

The Town solicited proposals for professional engineering services. Only two firms submitted qualifications.  McAdams received the highest score and is determined to be the most qualified firm to complete the scope of work. These services include surveying (UAS), subsurface utility engineering, roadway and hydraulic design, geotechnical investigation and consultation, erosion control planning, and bid support.  As a reminder, these repairs are reimbursable through FEMA-PA. 

McAdams has proposed a scope of work that includes the following major components: 

- UAS-based Survey and Topographic Mapping 

- Subsurface Utility Engineering (SUE) 

- Roadway and Drainage Design 

- Geotechnical Investigation and Design 

- Erosion Control Design and Permitting 

- Project Administration and Bid Support Services 

This proposal is focused on slope stabilization and drainage repair only. Reconstruction of the 

Page 163 of 179
{1}------------------------------------------------
full roadway is not included in this phase of work. The deliveries from this contract will enable the Town to bid the stabilization project for construction. 

**Fiscal Impact:** 

**Total Cost:** $142,287 (estimated) 

Funding Source: Emergency recovery funds and general fund contingency (if needed) Note: Some of these costs may be reimbursable through FEMA Public Assistance or other disaster recovery programs. 

## **BUDGET IMPACT:** 

## **Is this expenditure approved in the current fiscal year budget?** Yes 

**If no, describe how it will be funded.** n/a 