**3.1.a** 

# Burke County 

**==> picture [268 x 76] intentionally omitted <==**

# Water and Sewer System Asset Inventory and Assessment 

**==> picture [154 x 47] intentionally omitted <==**

March 2024 

**Packet Pg. 4**
{1}------------------------------------------------
**3.1.a** 

## Water System Asset Summary 

|**Asset**|**Summary**|
|---|---|
|Customer Connections|2,342|
|Water Distribution Piping|544,000 ft|
|Valves|1,000|
|Fire Hydrants|386|
|Elevated Storage Tanks|6|
|Booster Pump Stations|6|



**Packet Pg. 5**
{2}------------------------------------------------
**3.1.a** 

Sewer System Asset Summary 

|**Asset**|**Summary**|
|---|---|
|Customer Connections|185|
|Gravity Collection Sewer|101,480 ft|
|Manholes|427|
|Pump Stations|4|
|Force Main|63,320 ft|
|Air Relief Manhole|14|



**Packet Pg. 6**
{3}------------------------------------------------
**3.1.a** 

Definitions 

- Asset Inventory and Assessment – Developing a tangible record of all system assets and their condition. 

• Master Plan – A guide for future capital projects that will be required to best serve your customers. 

• Asset Management Plan – A tactical plan for managing infrastructure to minimize the total operation and maintenance costs while maintaining a desired level of service for your customers. 

**Packet Pg. 7**
{4}------------------------------------------------
**3.1.a** 

Scope of Work • Phase I • Data Collection • GIS Mapping Updates • Phase II • Hydraulic Modeling and Analysis (Water and Sewer) • Field Program • Flow Monitoring • Smoke Testing • CCTV • Wastewater Pump Station Inspections and Testing • Elevated Storage Tank and Booster Pump Station Inspections • Asset Management Plan 

**Packet Pg. 8**
{5}------------------------------------------------
**3.1.a** 

# Asset Management Framework 

**==> picture [294 x 283] intentionally omitted <==**

**----- Start of picture text -----**<br>
1. Current<br>State of<br>Assets<br>5. Long‐Term  2. Level of<br>Funding Plan Service<br>Asset<br>Management<br>4. Minimum<br>3. Critical<br>Life Cycle<br>Assets<br>Cost<br>**----- End of picture text -----**<br>


**Packet Pg. 9**
{6}------------------------------------------------
**3.1.a** 

## 1. Current State of Assets 

• The first step of asset management is understanding the current state of all system assets. This step of the process will provide answers to the following questions: 

**==> picture [219 x 211] intentionally omitted <==**

**----- Start of picture text -----**<br>
1. Current<br>State of Assets<br>5. Long‐Term 2. Level of<br>Funding Plan Service<br>Asset<br>Management<br>4. Minimum 3. Critical<br>Life Cycle Cost Assets<br>**----- End of picture text -----**<br>


- What assets do I own? 

- Where are they located? 

- What condition are the assets in? 

- What is the remaining useful life of the assets? 

**Packet Pg. 10**
{7}------------------------------------------------
**3.1.a** 

## Water System Map 

**==> picture [508 x 340] intentionally omitted <==**

**Packet Pg. 11**
{8}------------------------------------------------
**3.1.a** 

## Current GIS Data ‐ Water 

- Lack of connectivity for water lines 

- No shapefiles for other water system 

   - components (valves, hydrants, meters, etc.) 

- Lack of attributes for water lines 

      - Size 

      - Pipe material 

      - Age 

      - Condition 

      - Length 

**==> picture [167 x 284] intentionally omitted <==**

**Packet Pg. 12**
{9}------------------------------------------------
**3.1.a** 

## Sewer System Map 

**==> picture [498 x 333] intentionally omitted <==**

**Packet Pg. 13**
{10}------------------------------------------------
**3.1.a** 

Current GIS Data ‐ Sewer 

- Lack of attributes 

   - Elevations 

   - Pipe material 

   - Age 

   - Condition 

**==> picture [163 x 139] intentionally omitted <==**

**==> picture [189 x 340] intentionally omitted <==**

**Packet Pg. 14**
{11}------------------------------------------------
**3.1.a** 

**==> picture [792 x 512] intentionally omitted <==**

**----- Start of picture text -----**<br>
Data Collection Process<br>Willis Engineers to utilize data<br>to update GIS features and<br>associated attribute tables.<br>Publish set of map books<br>County to provide<br>available mapping<br>data including<br>record drawings<br>and other mapping<br>resources<br>County staff to review<br>published map books and<br>mark up known errors and<br>inconsistencies<br>Attachment: Budget Retreat AIA Presentation 2024 03 07-2  (4319 : Water & Sewer System AIA (Asset<br>**----- End of picture text -----**<br>


**==> picture [91 x 19] intentionally omitted <==**

**----- Start of picture text -----**<br>
Packet Pg. 15<br>**----- End of picture text -----**<br>
{12}------------------------------------------------
**3.1.a** 

Maintenance Maps and GIS Database 

**==> picture [455 x 297] intentionally omitted <==**

**Packet Pg. 16**
{13}------------------------------------------------
**3.1.a** 

## 2. Level of Service 

- The second step of asset management is knowing the level of service required of the utility. 

- There are various elements that define the level of service of a system, such as: 

**==> picture [219 x 211] intentionally omitted <==**

**----- Start of picture text -----**<br>
1. Current<br>State of Assets<br>5. Long‐Term 2. Level of<br>Funding Plan Service<br>Asset<br>Management<br>4. Minimum 3. Critical<br>Life Cycle Cost Assets<br>**----- End of picture text -----**<br>


- Quality 

- Quantity 

- Reliability 

- Environmental Standards 

- Safety Standards 

**Packet Pg. 17**
{14}------------------------------------------------
**3.1.a** 

## Water Distribution Model 

- WaterGEMS Software 

- Fire Hydrant Testing for Model Calibration 

- Identify Potential Deficiencies 

   - Normal Flow 

   - Fire Flow 

- Simulate Demand from Future Development 

**==> picture [280 x 285] intentionally omitted <==**

**Packet Pg. 18**
{15}------------------------------------------------
**3.1.a** 

## Sewer Collection Model 

- Analyze Flow 

- Calibrate Model 

- Evaluate Potential Sources of Infiltration and Inflow 

- Identify Deficiencies 

- Simulate Future Development 

- Assist in Development of Capacity Assurance Worksheets 

•Location •Pipe description 

• Deficiencies? • Identify future assets 

•Average Daily Flow •Peak Flow 

Total Capacity 

Existing Flows 

Available Capacity 

•Sufficient Future capacity? Development • Identify future assets 

**Packet Pg. 19**
{16}------------------------------------------------
**3.1.a** 

**==> picture [470 x 353] intentionally omitted <==**

**----- Start of picture text -----**<br>
Field Program<br>Sewer Collection Model<br>Flow Monitoring<br>Smoke Testing<br>Closed‐Circuit<br>Television (CCTV)<br>**----- End of picture text -----**<br>


**Packet Pg. 20**
{17}------------------------------------------------
**3.1.a** 

Flow Monitoring 

**==> picture [194 x 264] intentionally omitted <==**

• Flow Meters 

• Level Monitors 

- Rain Gauges 

**==> picture [202 x 258] intentionally omitted <==**

**Packet Pg. 21**
{18}------------------------------------------------
**3.1.a** 

Smoke Testing 

- Detects Manhole Leaks 

- Defective Sewer Cleanouts 

- Mainline Issues Including Cracks 

- Sewer Lateral Deficiencies 

- Storm Drainage Connections 

- Unknown Connections 

**==> picture [195 x 259] intentionally omitted <==**

**==> picture [196 x 258] intentionally omitted <==**

**Packet Pg. 22**
{19}------------------------------------------------
**3.1.a** 

Closed‐Circuit Television (CCTV) 

**==> picture [416 x 281] intentionally omitted <==**

**Packet Pg. 23**
{20}------------------------------------------------
**3.1.a** 

## Pump Station Inspections and Testing 

- Drawdown Testing 

- Condition Assessment 

   - Mechanical 

   - Electrical 

   - Structures 

   - Site Safety (Access, Fencing, Locks, etc.) 

   - Other Site Components 

**==> picture [249 x 149] intentionally omitted <==**

**==> picture [249 x 157] intentionally omitted <==**

**Packet Pg. 24**
{21}------------------------------------------------
**3.1.a** 

## 3. Critical Assets 

- Bottom line – assets fail! The steps that come after failure are what is important. 

• Not all failures are the same – some are more **critical** than others. 

- Which assets are the most critical? 

1. Current State of Assets 

**==> picture [219 x 95] intentionally omitted <==**

**----- Start of picture text -----**<br>
5. Long‐Term 2. Level of<br>Funding Plan Service<br>Asset<br>Management<br>**----- End of picture text -----**<br>


**==> picture [159 x 73] intentionally omitted <==**

**----- Start of picture text -----**<br>
4. Minimum 3. Critical<br>Life Cycle Cost Assets<br>**----- End of picture text -----**<br>


**Packet Pg. 25**
{22}------------------------------------------------
**3.1.a** 

What Makes an Asset Critical? 

**==> picture [468 x 284] intentionally omitted <==**

**----- Start of picture text -----**<br>
What are the<br>consequences of<br>failure?<br>What is the  What are the<br>likelihood of  costs associated<br>failure? with failure?<br>How would this<br>How could this  Asset  failure effect the<br>asset fail? Criticality required level of<br>service?<br>**----- End of picture text -----**<br>


**Packet Pg. 26**
{23}------------------------------------------------
**3.1.a** 

## 4. Minimum Life Cycle Cost 

- The fourth step is evaluating the life cycle cost of the system 

• Integrate the first three steps in the system 

- Identify maintenance programs or Capital Improvement Projects 

**==> picture [219 x 153] intentionally omitted <==**

**----- Start of picture text -----**<br>
1. Current<br>State of Assets<br>5. Long‐Term 2. Level of<br>Funding Plan Service<br>Asset<br>Management<br>**----- End of picture text -----**<br>


**==> picture [61 x 61] intentionally omitted <==**

**----- Start of picture text -----**<br>
4. Minimum<br>Life Cycle Cost<br>**----- End of picture text -----**<br>


**==> picture [61 x 61] intentionally omitted <==**

**----- Start of picture text -----**<br>
3. Critical<br>Assets<br>**----- End of picture text -----**<br>


**Packet Pg. 27**
{24}------------------------------------------------
**3.1.a** 

# What Makes up the System’s Life Cycle Cost? 

**==> picture [678 x 77] intentionally omitted <==**

**----- Start of picture text -----**<br>
Purchase of Operations<br>Capital System Life<br>Treated and Personnel Sales<br>Projects Cycle Cost<br>Water Maintenance<br>**----- End of picture text -----**<br>


**Packet Pg. 28**
{25}------------------------------------------------
**3.1.a** 

## 5. Long‐Term Funding Plan 

- Long‐term funding plan – critical to implementation of an Asset Management Plan 

- Includes operation and maintenance costs and Capital Improvement Projects 

- Long‐term sustainable operation of the system 

- Qualified municipal advisor 

**==> picture [61 x 60] intentionally omitted <==**

**----- Start of picture text -----**<br>
5. Long‐Term<br>Funding Plan<br>**----- End of picture text -----**<br>


- Rate Study by Raftelis 

**==> picture [15 x 20] intentionally omitted <==**

1. Current State of Assets 

2. Level of Service Asset Management 

**==> picture [18 x 15] intentionally omitted <==**

4. Minimum Life Cycle Cost 

**==> picture [61 x 61] intentionally omitted <==**

**----- Start of picture text -----**<br>
3. Critical<br>Assets<br>**----- End of picture text -----**<br>


**Packet Pg. 29**
{26}------------------------------------------------
**3.1.a** 

## Steps to Making Funding Decisions 

**==> picture [592 x 282] intentionally omitted <==**

**----- Start of picture text -----**<br>
What? When? How?<br>• What projects  • When do these  • How will these<br>will take place  projects need to  projects be<br>over the next 20  be completed? funded?<br>years? •Immediate rehab  •System revenues<br>•Repairs to assets in  needs •Capital reserves<br>poor condition •Replacement of a  •Federal/State grants<br>•Replace assets that  sewer line for  •Federal/State loans<br>limit the level of  capacity within the<br>service next 10 years<br>**----- End of picture text -----**<br>


**Packet Pg. 30**
{27}------------------------------------------------
**3.1.a** 

|Getting Started<br>**Plan**<br>Develop a scope of work<br>that will lead to developing<br>an Asset Management<br>Plan|**Create**<br>Create the Asset<br>Management Plan based<br>on the five framework<br>questions|**Implement**<br>Put the plan to use –<br>implement the Asset<br>Management Plan|
|---|---|---|



**Packet Pg. 31**
{28}------------------------------------------------
**3.1.a** 

## Timeline 

**==> picture [504 x 319] intentionally omitted <==**

**----- Start of picture text -----**<br>
March 2024<br>Phase I begins with data collection and GIS mapping updates<br>June 2024<br>Phase I complete<br>July 2024<br>Phase II begins with hydraulic modelling and field program<br>December 2024<br>Complete field program and develop CIP<br>March 2025<br>Review draft rate study and system development fee analysis with Board<br>April 2025<br>Finalize and publish Asset Management Plan<br>**----- End of picture text -----**<br>


**Packet Pg. 32**