Burke County, North Carolina 

## Dear Board: 

I’m pleased to present you with the Capital Improvement Plan (CIP) for fiscal years 2025-2029. The CIP serves as a long-range planning tool used to help the County match revenues with major capital needs (items/projects with a unit cost over $50,000) over a five-year period. The projects in the CIP are derived from Board Goals, citizen requests, and departmental recommendations. Moving forward, a summary version of the CIP will be provided with my recommended budget for each fiscal year that aligns with the projects. 

Burke County’s CIP Plan is a five-year investment plan.  The CIP effectively coordinates the addition, renovation or replacement of County-owned facilities, infrastructure, equipment, and land acquisition.  It is important to note that the County is also statutorily responsible for certain public schools and community college related capital. 

## **Major Factors Impacting Capital Planning** 

**Revenue –** All budgets are constrained by available revenues and that is no different for Burke County. Capital projects are prioritized so that available funds are allocated based on need, Board priority, and their impact on service provision.  Fiscal year 2024-2025 will be a year of transition and movement for many of the major projects that are included in our plan.  Following an elongated planning stage, the most recent twelve (12) months can be summarized as advancement.  The County intends to include funding for a variety of County projects, with a special emphasis on building stock, infrastructure, and technology.  Included in the 2024-2025 budget and the FY 20252029 Capital Improvement Plan is consideration for a dedicated funding source. 

**Building Stock** – As County facilities age, there is a need to renovate buildings to meet ADA, safety standards, service delivery demands and citizen expectations. During the 2020 fiscal year, the county contracted with outside consultants ( _Moseley Architects_ ) to facilitate a 30-year facilities master plan that took stock of all major county facilities. This detailed report was presented to the Board of Commissioners at your March 2[nd] , 2023, working session and will continue to be a point of emphasis in project prioritization and the annual updating of our execution plan – staff worked to separate the top recommendations into short, medium, and long-term strategies. 

As part of the FY 25-29 CIP plan, we will share recommendations of strategy based on highest need, timing, and funding source. 

**Infrastructure** – The report showed that many facilities are near their end of life in the county’s core buildings, the importance of infrastructure cannot be understated.  Several projects are underway across the County to update outdated systems, improve operating efficiencies and reduce repair costs including major HVAC repairs and roof replacements.  The Board of Commissioners approved to participate in a water/sewer asset inventory assessment (AIA) feasibility study that will evaluate every major piece of infrastructure across the county.  The study was funded with a state grant in the amount of $500,000 – and was awarded to Willis Engineering.  The county can enhance design, reduce operational costs, and improve effectiveness through infrastructure improvements. 

**Technology:** Citizens expect their County to be technologically savvy.  As we move forward with the foundation of our technology systems in place, we will shift our focus to long-term efficiency and systems synchronization. The FY 25-29 CIP continues to invest into technology with a focus on engaging an outside consultant to help draft 

**Packet Pg. 366**
{1}------------------------------------------------
**3.3.b** 

CAPITAL IMPROVEMENT PLAN FY 2025-2029 

CAPITAL IMPROVEMENT PLAN FY 2025-2029 

a long-term I.T. strategic plan – our principles include increased automation ( _with a focus on increasing business intelligence_ ), customer service, data security and citizen engagement.  Our focus in the short term will be interactive citizen interface, internal organizational communication and measuring the utilization percentage of our current ERP systems ( _Munis_ ) – which seems drastically underutilized.  This measurement has begun in the second half of the current fiscal year.  Munis software experts spent two (2) full days on site for a full technical assessment of our utilization and system setup – which led to a full report on enhancement and efficiency improvements.  Our team is approximately 80% through the facilitation and plan to evaluate the impact and make a long-term decision by June 30, 2025. 

A secondary, yet critical component of our technology systems is tax administration.  The County has long been a user of NCPTS (a Farragut System) for all components of tax administration.  The annual cost of the system is approximately $160,000 – and like Munis, the County’s utilization and expertise in the system is at times limited. The 2024-2025 fiscal year will likely be a similar year of evaluation – as the county, at the vendor’s recommendation, transitions systems updates and administrative efforts to Farragut ($50,000) and purchased four (4) hours monthly of on-site specialized training – with a goal of making a long-term software relationship decision by January 1, 2025, ahead of the 2027 revaluation cycle. 

**– Maintenance of County Facilities** The County continues to identify areas for improvement to general county facilities. The CIP plan includes a sinking fund that is dedicated to various projects across the organization. 

## **Revenue Sources: - Prioritized in this order:** 

**Grant Funds:** The County continues to aggressively pursue state and federal grant funding and has been successful in many of these efforts. 

**Capital Reserve Funds:** The proposed funding for Capital Reserve Funds is a dedicated tax rate of 1.1 cents or approximately $1.2 MM annual re-occurring funds. 

**Pay-As-You-Go:** Whenever possible, pay-as-you-go funding is the preferred method of funding CIP projects. For large capital projects, this is not a feasible option. 

**Debt Proceeds:** Some major capital projects are best funded through bank or bond borrowings that have a longer payback term.  These debt service payments would be paid from the debt service fund – which is funded through the dedicated Capital Reserve Fund. 

## **Conclusion** 

The following pages of this document provide additional detail on the projects listed above as well as those in future planning years. This document is considered a “living” document that serves as a planning guide and will be adjusted as existing projects change and new needs arise. 

Respectfully submitted, 

Brian C. Epley County Manager 

**Packet Pg. 367**
{2}------------------------------------------------
**3.3.b** 

CAPITAL IMPROVEMENT PLAN FY 2025-2029 

CAPITAL IMPROVEMENT PLAN FY 2025-2029 

## BURKE COUNTY CAPITAL IMPROVEMENT PLAN 

## County Profile 

Burke County is located in the west central section of North Carolina’s mountain region, with a population of about 90,000 people and a diverse economy that includes industrial products from technological, furniture, medical, chemical, machine component and textile manufacturers. Burke County is home to the western campus of the North Carolina School of Science and Mathematics and Western Piedmont Community College. The County’s median household income is $48,142 and unemployment remains steadily below four percent. 

## County Commissioners 

Burke County is led by the Board of County Commissioners, a five (5) member board, who are elected at large to serve the citizens of Burke County.  The Commissioners annually work through a strategic planning process which is the essential first step in the development of a results-based accountability system that defines the Board’s strategy and policy direction for achieving organizational and community goals. 

## **FY 2024-2025 Board Strategic Goals** 

The Board’s strategic goals are broken into five (5) focus areas: Community Advancement, Economic Growth & Sustainment, Public Safety & Well-Being, Fiscal Stewardship and Employer of Choice. 

In March 2023, the Board of Commissioners held their annual planning session that provided the initial direction to draft the County’s inaugural long term strategic plan.  The FY 24-25 planning session (March 7 & March 8, 2024) will look to maintain the momentum created during 2023 and provide meaningful updates to the strategic plan.  These goals guide budget prioritization, development, and implementation.   Several of the key goals associated with the FY 24-25 strategic plan are associated with multi-year capital planning and a focus on a developed deferred maintenance plan and building stock replacement.  These long-term commitments are further complimented by the County’s comprehensive master facility plan that was completed during 2020. 

## Fiscal Management 

In addition to the strategic planning process, the County has also developed a set of financial policies that are reviewed and approved by the Board to guide the County in the financial management of all funds. Although North Carolina local governmental units must adhere to the requirements set forth in the North Carolina Local Government Budget and Fiscal Control Act, the financial policies approved by the Board are often more stringent than State requirements to assure that Burke County will continue to function in a very fiscally sound manner. 

The Board has included a strategic plan for adopting a minimum unassigned fund balance policy of 25%.  As of June 30, 2023, the general fund unassigned fund balance percentage is 32.88%.   The Board receives ongoing financial information and projections that provide them with regular comprehensive financial updates. 

**Packet Pg. 368**
{3}------------------------------------------------
**3.3.b** 

CAPITAL IMPROVEMENT PLAN FY 2025-2029 

CAPITAL IMPROVEMENT PLAN FY 2025-2029 

## Current and On-Going Projects 

Several capital expenditures included in the 2024-2025 CIP plan are included in the current operating budget and include all rolling stock, solid waste collection site construction, technology investments and HVAC infrastructure (boilers/chillers). 

## **Land Stock Development** 

_This area of the plan will be reserved for future land stock acquisition and management._ 

## **Current Capital Expenditures** 

## Current Capital Reserve Planning 

During the 2024 budget process, the County has begun strategically planning for long-term operational capital investments.  Moving forward, during the annual budget process, the County has developed an operational capital reserve fund in collaboration with all County departments.  The fund is funded annually through the budget process, based on planned proportionate project amounts (ahead of their planned timeline) and available resources - it will also experience investment annually based on available resources remaining at the end of a budget cycle. 

The County’s 2020 facility study continues to be the primary tool used for outyear capital prioritization and funding alignment. 

Statutorily, the Capital Reserve Fund is dollars set aside for future capital needs; however, there remains a certain fluidity and adaptability that is critical to allow for constant capital prioritization.  The Capital Reserve Fund is used to plan and forecast outyear non-major capital needs.  Major capital projects - primarily those that are in excess of $1MM and are completed over a multi-year period are outlined separately and accounted for via separate project ordinances and funds. See below for details of the Capital Reserve Fund, which are part of the FY 24-25 CIP and budget draft: 

**Technology & Automation** : Increasingly, services that we have once offered locally are being developed and updated within the Cloud.  Although more expensive, the Cloud offers present opportunities for easy mobile access, increased collaboration, and allows users to work from anywhere.  It ensures everyone operates with the most recent product a vendor has to offer.  Beginning with a complete Enterprise Resource Planning (ERP) review, transitioning to more cloud-based services, email systems and most recently electronic timekeeping will all be priorities of capital reserve planning. 

Security and user education remain an extreme priority.  We are researching artificial intelligence (AI) systems to help in sifting through network and email traffic to root out malware and infections.  Funding requirements for these system-wide upgrades that include increased mobility, security, and efficiency over the next five (5) years will require proactive funding.  The annual County I.T. investment and strategy will become more centralized, and more of a focal point of the budgeting process.  This level of needed investment will be critical as the team continues to refine processes and pursue our organizational goals related to LEAN principles and efficiency.  As part of the FY 25-29 

**Packet Pg. 369**
{4}------------------------------------------------
**3.3.b** 

CAPITAL IMPROVEMENT PLAN FY 2025-2029 

CAPITAL IMPROVEMENT PLAN FY 2025-2029 

capital plan, the County will begin envisioning the first ever I.T. strategic plan – with a very specific purpose of advancing synchronization and developing a clear I.T. vision. 

## **Major Roofing Projects & HVAC** : 

**Foothills (FHEC) HVAC Replacements** : The 2023-2024 CIP plan included replacement of the roof top HVAC units at the Foothills Higher Education Center (FHEC).   The total project cost was $478,000 replaced 13 of the more than 20 roof top units. 

**Foothills (FHEC) Roof Replacements** : Included in the five (5) year plan is $1.2MM for a complete roof replacement. 

**Courthouse Roof** – The roof of the courthouse is also compromised in limited areas.  The FY 24-25 CIP includes a major renovation project for the courthouse of approximately $2.1MM.  The project is highly logistical and is intended to invest in major mechanical but also address building operational compression.  This is a design/build project, with a joint venture of Holland & Hamrick Architects along with BEAM construction.  Evaluation of the flat membrane roof is underway and intended to be part of the project budget. 

There are other roof maintenance plans in the County’s operational budgets – excluded from this CIP. 

**Major Rolling Stock** :  Burke County staff annually evaluate the condition and utilization of the rolling stock fleet. As of January 2024, the County’s fleet was comprised of 236 vehicles and the average miles were 76,209.  The Burke County budget team is working on drafting a formal rolling stock replacement policy and a staggard replacement schedule to be included in the CIP plan moving forward.  The policy, which will include an annual evaluation of each vehicle’s condition and mileage, would be the predictive data analytic – which assumes mechanical and safety standards remain above level 3 on the County’s condition rating scale (1 = bad / 5 =good). 

FY 24-25 will be the second budget year of a 5-year capital lease obligation that provides for the replacement of five (5) ambulances – which anticipate delivery in Q2 of 2024.  The EMS department has a total fleet of 16 ambulances and utilizes 9 per shift – many of the existing fleets have more than 250,000 miles and are at end of life.  The total lease amount is $2,113,780 - $422,756 payable over a five (5) year period.  Other rolling stock such as Quick Response Vehicles (QRV) will be funded annually on a pay-as-you-go basis. The FY 24-25 budget will include one (1) QRV at an estimated total cost of $150,000.  The prior year budget replaced two (2) QRVs and added a transit unit at a cost of $350,000. 

The annual appropriation to the Sheriff’s Office, based on prior year experiences and predictive analytics on replace vs. repair indicates a needed total cost for FY 24-25 is to be approximately $850,000 – up (10%) from $774,000 in the prior year.  Sheriff rolling stock is funded pay-as-you-go inside the Sheriff’s department budget. Approximately 57% of the total fleet is operated by either the Sheriff’s office or Emergency Services departments. Other rolling stock investments include replacement of several other departmental use vehicles. 

**Public Safety Radios** :  Interoperable communications were identified in the General Assembly's Criminal Justice Information Network report of 1995 as a critical need for public safety agencies when responding to emergencies. The mobile VIPER towers provide limited local area communications where there is none. The VIPER towers can provide 800MHz, VHF, and UHF.   VIPER currently operates a Motorola SmartZone 800 MHz system with 92 remote voice radio transmitter sites across the state of North Carolina.  Burke County operates on the VIPER system 

**==> picture [91 x 19] intentionally omitted <==**

**----- Start of picture text -----**<br>
Packet Pg. 370<br>**----- End of picture text -----**<br>
{5}------------------------------------------------
**3.3.b** 

CAPITAL IMPROVEMENT PLAN FY 2025-2029 

CAPITAL IMPROVEMENT PLAN FY 2025-2029 

for public safety mobile communication – historically with public safety rated Motorola radios.  The majority of the fleet was purchased on the onset of the system and had reached both end of life for production and support from the manufacturer.  Beginning in FY 23-24, Burke County included a radio replacement plan in the CIP plan that required an annual investment of $205,000 per year through FY 28.   During 2023-2024, the County received a $400,000 technology rebate credit from Motorola that can be exercised on radio purchase if the total purchase amount exceeds $1.5MM and is prior to December 31, 2024 – this package also offers deep volume discounts of up to 30% per unit. To accomplish the $1.5MM acquisition and benefits of the discounts, the county is leveraging a multi-jurisdictional capital acquisition with several municipal partners and volunteer fire departments.  The county also reprioritized out year capital needs to increase the allocation for radios to $645,000 (2023-2024).  The FY 24-25 CIP plan continues to allocate $205,000 per year moving forward. 

## **Multi-Year Capital Planning & Capital Reserve Fund** 

## **GOVERNMENTAL ACTIVITIES OUT-YEAR NON-MAJOR** 

|**Project**|**Total Project Cost**||**2023-2024**||**2024-2025**||**2025-2026**||**2026-2027**||**2027-2028**||**2028-2029**||**5 YEAR TOTAL**|
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|||||||||||||||||
|Clerk and GoverningBoard FacilityProjects|75,000||-||-||25,000||25,000||25,000||-||75,000|
|ROD Indexing|170,000||-||-||85,000||85,000||-||-||170,000|
|||||||||||||||||
|Migrate Servers from Hyperflex to Scale environment|250,000||125,000||125,000||-||-||-||-||250,000|
|Jail network and wifi|50,000||15,000||15,000||15,000||5,000||-||-||50,000|
|Services buildingnetwork replacement|80,000||20,000||20,000||20,000||20,000||-||-||80,000|
|BCECC network replacement,radio network,wifi|150,000||50,000||50,000||50,000||-||-||-||150,000|
|Other operational system upgrades - see detail tab|648,000||-||227,500||302,500||93,000||25,000||-||648,000|
|||||||||||||||||
|FHEC - Roof Replacement|1,200,000||-||225,000||225,000||250,000||250,000||250,000||1,200,000|
|||||||||||||||||
|New EMS Base - Location TBD|625,000||||-||125,000||250,000||-||250,000||625,000|
|||||||||||||||||
|Cooperative Extension - General Capital|80,000||||15,000||50,000||15,000||||||80,000|
|||||||||||||||||
|I.T. Strategic Plan|125,000||62,500||62,500||-||-||-||-||125,000|
|Organizational Wide Public SafetyMobile Radio Replacement 212|1,055,000||645,000||205,000||205,000||-||-||-||1,055,000|
|||||||||||||||||
|Field 3 lights at Reep park|180,000||90,000||90,000||-||-||-||-||180,000|
|Pavingofparkinglots at Reepand Simpson|70,000||25,000||25,000||20,000||-||-||-||70,000|
|Replace two 20year Kubota mowers|55,000||27,500||27,500||-||-||-||-||55,000|
|||||||||||||||||
||4,568,000<br>$|$|1,060,000|1,087,500<br>$||1,012,500<br>$||633,000<br>$||275,000<br>$||500,000<br>$||$|4,568,000<br>|



|**WATER/SEWER**|**WATER/SEWER**|**ACTIVITIES**|**ACTIVITIES**|**OUT-YEAR NON-MAJOR**|**OUT-YEAR NON-MAJOR**|**OUT-YEAR NON-MAJOR**|**OUT-YEAR NON-MAJOR**|**OUT-YEAR NON-MAJOR**|**OUT-YEAR NON-MAJOR**|||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|**Project**|**Total Project Cost**||**2023-2024**||**2024-2025**||**2025-2026**||**2026-2027**||**2027-2028**||**2028-2029**||**5 YEAR TOTAL**|
|Water Meter Mechanics replacmeent - ALL|485,000||320,000||305,000||-||-||-||-||625,000|
|Creek Bank Stabalization|120,000||120,000||-||-||-||-||-||120,000|
||605,000<br>$|$|440,000|305,000<br>$||-<br>$||-<br>$||-<br>$||-<br>$||$|745,000|



**Packet Pg. 371**
{6}------------------------------------------------
**3.3.b** 

CAPITAL IMPROVEMENT PLAN FY 2025-2029 

CAPITAL IMPROVEMENT PLAN FY 2025-2029 

|**SOLID WASTE ACTIVITIES OUT-YEAR NON-MAJOR**|**SOLID WASTE ACTIVITIES OUT-YEAR NON-MAJOR**|**SOLID WASTE ACTIVITIES OUT-YEAR NON-MAJOR**|**SOLID WASTE ACTIVITIES OUT-YEAR NON-MAJOR**|**SOLID WASTE ACTIVITIES OUT-YEAR NON-MAJOR**|**SOLID WASTE ACTIVITIES OUT-YEAR NON-MAJOR**|**SOLID WASTE ACTIVITIES OUT-YEAR NON-MAJOR**|**SOLID WASTE ACTIVITIES OUT-YEAR NON-MAJOR**||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
|**Project**<br>Roll Off Truck Purchase|**Total Project Cost**<br>620,000<br>$|$|**2023-2024**<br>110,000|**2024-2025**<br>110,000<br>$ 100,000<br>-<br> <br>125,000<br>80,000<br>415,000<br>$|**2025-2026**<br>100,000<br>$ 100,000<br>-<br>125,000<br> <br>80,000<br>405,000<br>$|**2026-2027**<br>100,000<br>$ -<br>300,000<br>-<br>80,000|**2027-2028**<br>100,000<br>$ -<br>300,000<br>-<br>-<br>400,000<br>$||**2028-2029**<br>100,000<br>$ -<br>325,000<br>-<br> <br>-||$ $ $ $ $|**TOTAL**<br>620,000<br>200,000<br>925,000<br>250,000<br>240,000<br> <br>2,235,000<br>|
|New Scale Replacement<br>New Compactor<br>Cardboard Compactors<br>Collection Site Offices|200,000<br> <br>925,000||-<br>-||||||||||
||250,000||-||||||||||
||240,000||-<br>||||||||||
||2,235,000<br>$|$|110,000|||480,000<br>$|||425,000<br>$||$||



**==> picture [542 x 223] intentionally omitted <==**

**----- Start of picture text -----**<br>
BURKE COUNTY, NORTH CAROLINA<br>CAPITAL RESERVE ANALYSIS<br>FOR THE YEAR ENDED JUNE 30, 2024<br>PY ACTUAL CY ACTUAL PROJECTED<br>2022-2023 2023-2024 2024-2025 2025-2026 2026-2027 2027-2028 2028-2029<br>REVENUE SOURCES<br>General Fund Transfer - Revenue Replacement $ 10,000,000 $ - $ - $ - $ - $ - $ -<br>General Fund Transfer - Direct Cost Supplantation 3,500,000 2,729,116 - - - - -<br>General Fund Transfer - Local 1,000,000 1,610,000 1,087,500 1,012,500 633,000 275,000 925,000<br>Water / Sewer Transfer - - 305,000 - - - -<br>Solid Waste Transfer - 110,000 415,000 405,000 480,000 400,000 425,000<br>Other Revenue 65,273 250,000 10,000 10,000 10,000 10,000 10,000<br>Total Funding $ 14,565,273 $ 4,699,116 $ 1,817,500 $ 1,427,500 $ 1,123,000 $ 685,000 $         1,360,000<br>EXPENDITURE / PROJECTS<br>Major Projects - See detail Tab $ - $ 17,550,000 $ - $ - $ - $ - $ -<br>Non-Major Out Year Projects  - 1,610,000 1,807,500 1,417,500 1,113,000 675,000 925,000<br>Total Expenditures  - 19,160,000 1,807,500 1,417,500 1,113,000 675,000 925,000<br>Remaing Equity 14,565,273 104,389 114,389 124,389 124,389 134,389 559,389<br>**----- End of picture text -----**<br>


Major Facility Projects 

## **Long-Term Planning** 

On March 2, 2023, the Burke County Board of Commissioners analytically reviewed a comprehensive list of County capital needs – which has been fluidly updated since that point.  This listing was in part based on the 2020 facility analysis along with key deferred maintenance needs identified by staff.  The County has conducted several long-term studies for major capital that will prove vital as we focus on making sustainable and long-term capital investments: Commissioners prioritized these needs based on urgency and affordability.  See below for a short-term, mid-term, and long-term strategy of prioritization. 

## **Short-Term:** 

- Jonas Ridge Phase I & II 

- East Burke Collection Site 

- Indian Hills Pump Station 

- Courthouse Improvements 

- Storage Management Policies 

**Packet Pg. 372**
{7}------------------------------------------------
**3.3.b** 

CAPITAL IMPROVEMENT PLAN FY 2025-2029 

CAPITAL IMPROVEMENT PLAN FY 2025-2029 

## **Mid-Term:** 

- Health and Human Services Building 

- Animal Services Building 

- Emergency Medical Services Base #1 

- Regional Substance Abuse Rehabilitation Center 

- Fonta Flora Trail Boardwalk at Linville Dam 

- Fonta Flora Trail Eagles Nest Overlook and ADA pocket park 

## **Long-Term:** 

- Library Expansion 

- Solid Waste MSW Development 

- Water/Sewer Infrastructure 

- EMS Base Additions 

## **Short-Term Projects:** 

## **Jonas Ridge Collection Site** 

**==> picture [444 x 167] intentionally omitted <==**

- **Phase I & Phase II:** Jonas Ridge - The three-acre parcel owned by the County will house the new convenience site and convert the existing building into a community center with public restrooms. The Convenience site will have more room, additional drop off bins, and new compactors that make it easier to drop off trash. 

|||**Project**||**Cost**||**Source**||**Completion Date**|**Completion Date**|**Completion Date**|
|---|---|---|---|---|---|---|---|---|---|---|
||<br>**Phase I**|||**$1,900,000**||**Pay-as-you-go**||||<br>**5/1/2024**|
||**Phase II**|||**$800,000**||<br>**Pay-as-you-go**|||**12/31/2024**||



**Packet Pg. 373**
{8}------------------------------------------------
**3.3.b** 

CAPITAL IMPROVEMENT PLAN FY 2025-2029 

CAPITAL IMPROVEMENT PLAN FY 2025-2029 

**==> picture [460 x 177] intentionally omitted <==**

## **East Burke Collection Site** 

- **East Burke:** East Burke - The Convenience site will have more room, additional drop off bins, and new compactors that make it easier to drop off trash.  The estimated cost is approximately $1.5MM and is funded pay-asyou-go.  The County will review the RFP process in April 2023 – project completion should be early 2024. 

||**Project**||**Cost**||**Source**||**Completion Date**|
|---|---|---|---|---|---|---|---|
|<br>**East Burke Collection**|||**$1,517,000**||**Pay-as-you-go **||<br>**4/1/2024**|



## **Indian Hills Pump Station** 

- **Indian Hills Pump Station:** Located in East Burke, the Indian Hills sewer pump station is subject to frequent stream flooding and experiences excessive peak flows. The flooding has prevented County personnel from properly operating the station, due to access being blocked by flood waters. Excessive peak flows have caused seven sanitary sewer overflows (SSO’s) reaching surface waters over just the last three years. Therefore, the pump station site and access road need to be raised above flood level (2’ above BFE), and the pump station and force main need to be upgraded such that peak flows of up to 2,000 gpm can be handled. Another issue is that increased flood frequency and flood intensity have caused erosion of the streambank adjacent to the pump station (Drowning Creek). This erosion is threatening to undermine the pump station site and infrastructure. 

In addition, all equipment and maneuvering/access areas will be raised to 2’ above BFE (currently, only the pumps and electrical are above BFE). Finally, the eroding streambank of Drowning Creek will be stabilized – the streambank stabilization is funded and underway. 

The project will ensure continuous operation of this vital infrastructure located within the 100-year floodplain. 

||**Project**||**Cost**||**Source**||**Completion Date**|
|---|---|---|---|---|---|---|---|
|<br>**Indian Hills Pump Station**|||**$1,118,000**||**Grant - SWDF**||<br>**12/31/2025**|



**Packet Pg. 374**
{9}------------------------------------------------
**3.3.b** 

CAPITAL IMPROVEMENT PLAN FY 2025-2029 

CAPITAL IMPROVEMENT PLAN FY 2025-2029 

## **Courthouse Improvements** 

• **Courthouse:** The Burke County Courthouse, originally built in 1976, has been renovated twice.  Once in 2011 and again in 2020.  Overall, the building has been taken care of and renovated.  With investments in courthouse esthetics, flooring, mechanical, and structure, the building is suitable for continued use; however, there are roofing failures, most of the equipment infrastructure is end of life, lighting should be updated to LED, and other esthetics should be considered.  There are also significant needs in the HVAC realm, primarily in the basement – that if properly adapted, could create compression relief that allows for additional courtroom space and storage.  The estimated costs of these renovations are approximately $2.1MM. 

||**Project**||**Cost**||**Source**||**Completion Date**|
|---|---|---|---|---|---|---|---|
|<br>**Courthouse**|||**$1,000,000**||**Grant - SCIF**||<br>**12/31/2024**|
|**Courthouse**|||**$1,100,000**||**Pay-as-you-go **||**12/31/2024**|



## **- Mid Term Projects:** 

## **Health and Human Services Building** 

- **HRC:** The Burke County Human Resource Center (HRC) originally built in 1973, has reached its end of life.  Over time there have been many interior renovations, roof investments, and investments in mechanical systems.  The overall building score from the 2020 analysis was 2.42.  This approximately 75,000 square foot building houses approximately 320 full-time employees and is a critical function of service delivery. 

The last six (6) months have included a comprehensive space planning program that includes projections of demographics, staff surveys, & legislative changes. 

**==> picture [311 x 314] intentionally omitted <==**

**Packet Pg. 375**
{10}------------------------------------------------
**3.3.b** 

CAPITAL IMPROVEMENT PLAN FY 2025-2029 

CAPITAL IMPROVEMENT PLAN FY 2025-2029 

The space planning will be followed by site location civil/survey analysis.  A twelve (12) month due diligence process followed by twenty-four (24) months of construction.  If programmed at 10% needed growth and factored at $325 per square foot the speculative building cost is assumed at approximately $27MM – site due diligence, planning/engineering, and financing costs could add another 12.5-13% ($3MM) for a total estimated project cost of $30MM.  A 20-year financing through the issuance of Limited Obligation Bonds (LOBS) or bank installment is the recommended funding source. Due to the complexity of the project a Construction Manager at Risk CMAR procurement model is likely to produce the best outcome. 

||**Project**|**Cost**||**Source**||**Completion Date**|
|---|---|---|---|---|---|---|
|<br>**DHHS Building**||**$30,000,000**||**LOBS - Debt**||<br>**06/30/2026**|



- **Animal Services:** The Burke County Animal Services Building has reached its end of life.  This facility currently provides working space for 8 FTEs and has only 16 dog kennels and 24 cat cages.  A space planning document has been started and is currently under review by a consultant.  The estimated needed square footage is approximately 15,000 square feet.  A design/build procurement model is the recommended path forward. 

- **EMS Base #1** This critical piece of public safety infrastructure is currently located on property that is not owned by Burke County Government - the lease has expired and is non-renewable.  Not only, is the building lease non-renewable, but the quality of the building is also end of life and does not offer co-location of operational teams with EMS administration. 

The proposed replacement for EMS base 1 will serve as the administrative office for the EMS director, major, captains, and shift supervisor.  The County has completed property acquisition of approximately 4.25 acres that we believe, based on call demand data, will be a more strategic location to serve the pre-hospitalization needs of our citizens as well as provide the needed modernization and space allocation to ensure long-term stability for this public safety function.  This base is intended to be duly utilized as the county’s back up public safety answering point (PSAP) as well as the head quarters for community medicine and hospital transports. 

||**Project**|**Cost**||**Source**||**Completion Date**|
|---|---|---|---|---|---|---|
|**Animal Services / EMS**||**$13,000,000**||**Pay-As-You-Go**||**12/31/2027**|



## **Regional Substance Abuse Rehabilitation Center:** 

- **ARC:** The Appalachian Recovery Center: Collectively over the past three (3) fiscal years, Burke County Government has contracted with a professional consulting firm to develop a comprehensive evaluation of a regionally based and supported substance abuse and opioid rehabilitation facility.  This multi-year project has aimed to evaluate evidencebased community building strategies that could be implemented as a matter of public policy. The County Commissioners wanted a vision supported by data that will deliver a proven strategy that warrants continued success for Burke County and the region. The vision of the Board of Commissioners is to leverage public policy to generate cumulative attention to the myriad of ways in which the physical, social, ecological, cultural, and even spiritual qualities of a person are intimately intertwined – and how the community is impacted by substance abuse disorders and the inherent lack of regional resources. Burke County has identified a county owned facility that, with appropriate investment, could serve this needed population by housing a conglomerate of non-profit rehabilitation services.   The engineered cost estimated to fund an adaptive reuse of the former Burke/Catawba jail (50,000 sq ft.) is estimated to have a total cost of $12-15MM.  This is currently an un-funded top priority, and the county is working to identify grant funding opportunities – including State Medicaid expansion funds. 

**Packet Pg. 376**
{11}------------------------------------------------
**3.3.b** 

**==> picture [540 x 23] intentionally omitted <==**

**----- Start of picture text -----**<br>
CAPITAL IMPROVEMENT PLAN FY 2025-2029<br>**----- End of picture text -----**<br>


**==> picture [523 x 192] intentionally omitted <==**

**----- Start of picture text -----**<br>
CAPITAL IMPROVEMENT PLAN FY 2025-2029<br>Project  Cost  Source  Completion Date<br>ARC  $15,000,000  State/Federal Grants  TBD<br>Fonta Flora Trail Systems:<br>• Boardwalk and Eagles Nest Overlook: Burke County has remained focused on cultural capital<br>investments to improve access to outdoor activities and improve citizens quality of life while also positioning Burke<br>County as a regional outdoor economic development center.  Two (2) upcoming projects for the continued<br>investment into the Fonta Flora Trail systems require an investment of approximately $2.2MM.<br>Project  Cost  Source  Completion Date<br>Fonta Flora Investment  $2,200,000  Pay-as-you-go  TBD<br>**----- End of picture text -----**<br>


## **- Long Term Projects:** 

- Library Expansion 

- Solid Waste MSW Development 

- Water/Sewer Infrastructure 

- EMS Base Additions 

These longer-term projects are currently outside of the County’s five (5) year planning and funding window; however, they have begun the prioritization process – which is fluid and subject to reprioritization on an annual basis as new funding sources and decision-making data becomes available. 

|||Status|Funded in PY from GF|Amount Funded in|Grant Funding|Debt Funding|Total Funding|
|---|---|---|---|---|---|---|---|
|||||Capital Reserve||||
|**Building - Major Projects**||||||||
|||||||||
|Animal Services Building|6,000,000<br>$|Active - Design & Development|-|6,000,000|-|-|6,000,000|
|EMS Base #1 Relocation|7,000,000<br>$|Active - Design & Development|-|7,000,000|-|-|7,000,000|
|||||||||
|Courthouse Improvements|2,100,000<br>$|Active - Design & Development|-|1,100,000|1,000,000|-|2,100,000|
|Health/Human Services Building|30,000,000<br>$|Space Planning90%|-|-|-|30,000,000|30,000,000|
|Indian Hills PumpStation Replacment|2,500,000<br>$|Analysispart of AIA - Ongoing|-|-|1,118,000|-|1,118,000|
|Fonta Flora Trail Capital Investment|2,200,000<br>$|TBD|-|2,200,000|-|-|2,200,000|
|Fonta Flora Trail Capital Investment|355,918<br>$|In Design Phase Bridge Side Walk<br>Mattern & Craig|-|-|355,918|-|355,918|
|Over Mountain VictoryTrail Investment|392,258<br>$|FERC Grant from Duke|-|-|392,258|-|392,258|
|Jonas Ridge Phase I|1,500,000<br>$|To be completedQ1 2024|1,500,000|450,000|-|-|1,950,000|
|East Burke Collection Site|1,500,000<br>$|To be completedQ1 2024|1,500,000|-|-|-|1,500,000|
|Jonas Ridge Phase II|800,000<br>$|In Design Phase(Q3 2024)- Equinox|-|800,000|-|-|800,000|
|Regional Rehab Center|15,000,000<br>$|Planning- TimingTBD|-|-|15,000,000|-|15,000,000|
|EMS Station - New Construction|1,000,000<br>$|Not Funded - TBD|-|-|-|-|-|
|EMS Station - New Construction|1,000,000<br>$|Not Funded - TBD|-|-|-|-|-|
|LibraryExpansion|12,000,000<br>$|Not Funded - TBD|-|-|-|-||
|||||||||
|||Total|3,000,000|17,550,000|17,866,176|30,000,000|68,416,176|



**Packet Pg. 377**
{12}------------------------------------------------
**3.3.b** 

CAPITAL IMPROVEMENT PLAN FY 2025-2029 

CAPITAL IMPROVEMENT PLAN FY 2025-2029 

## Major Facility Projects Funding 

Major facility expansions, upgrades, and renovations are not normal reoccurring parts of operations and typically require a debt structured funding source.  See below for a holistic review of Burke County’s debt portfolio, long-term planning strategies, and capital expansion sustainability. 

Most often major facility projects require debt issuance that enables the cost of construction to be allocated for multiple periods.  Burke County staff is working with both Moody’s and S&P (bond rating agencies) to provide a much-needed update to the County’s financial position, financing policies and a macro analysis of the County’s economic future.  The result is a potential bond rating upgrade, which will certainly prove meaningful as Burke County continues to execute the CIP plan proposal.  Bond rating provides investors with the much-needed objective perspective of the risk associated with County borrowings – thus a better rating often leads to lower interest rates and savings of taxpayer dollars.  The last review from Moody’s was completed in October of 2021.  See below for the summary: 

**==> picture [324 x 362] intentionally omitted <==**

Strengths –Very strong credit position. –Robust financial position. –Light debt and pension burden with negligible liability. –Fund balance and Cash balance as percentages of operating revenues are inline to slightly above the US median and other Moody’s-rated counties. –Strong financial management. Challenges –Weak socioeconomic profile, relative to the assigned rating of Aa2. –Should consider formal financing and debt management policies. –Median family income is only $55,817 (4th quartile) of the US level. 

**Packet Pg. 378**
{13}------------------------------------------------
**3.3.b** 

CAPITAL IMPROVEMENT PLAN FY 2025-2029 

CAPITAL IMPROVEMENT PLAN FY 2025-2029 

**Existing Debt Load as of June 30, 2023** 

**==> picture [541 x 144] intentionally omitted <==**

**----- Start of picture text -----**<br>
Governmental Activities Beginning Balance Additions Reductions Ending Balance<br>General Obligation Debt $ 235,000 $ - $ (235,000) $ -<br>Notes from Direct Borrowings 44,485,000 - (5,670,000) 38,815,000<br>Premium on Debt Issues 3,054,168 - (211,485) 2,842,683<br>Other Post-Employment Benefits 17,911,185 - (1,697,848) 16,213,337<br>Net Pension Liability 5,693,266 15,345,735 - 21,039,001<br>Net Pension Liability (LEOSSA) 3,438,828 - (596,667) 2,842,161<br>Compensated Absences 2,274,322 2,250,886 (2,112,567) 2,412,641<br>Total Governmental Activities $ 77,091,769 $ 84,164,823<br>**----- End of picture text -----**<br>


**==> picture [540 x 295] intentionally omitted <==**

**Packet Pg. 379**
{14}------------------------------------------------
**3.3.b** 

CAPITAL IMPROVEMENT PLAN FY 2025-2029 

CAPITAL IMPROVEMENT PLAN FY 2025-2029 

**==> picture [540 x 193] intentionally omitted <==**

- The County’s debt capacity is represented by the total amount of outstanding long-term debt and is a key indicator used by banks and bond raters to assess future borrowing ability. 

- The County’s general fund debt funding requirement for FY 24-25 is approximately 5.6% of the general fund expenditures. 

**==> picture [402 x 210] intentionally omitted <==**

**----- Start of picture text -----**<br>
Annual Debt Service Budget<br> $6,000,000<br>$5,440,000<br> $5,000,000<br> $4,000,000<br> $3,000,000<br>$2,055,000<br> $2,000,000<br> $1,000,000<br> $-<br>2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035<br>**----- End of picture text -----**<br>


**Packet Pg. 380**
{15}------------------------------------------------
**3.3.b** 

CAPITAL IMPROVEMENT PLAN FY 2025-2029 

CAPITAL IMPROVEMENT PLAN FY 2025-2029 

**==> picture [540 x 190] intentionally omitted <==**

## **Bond Rating** 

- The County is currently rated Aa2 by Moody’s – which is the third best rating that a County can have. 

- Management is currently working on several key recommendations that could improve that rating over time. The key limiter according to Moody’s is median family income. 

- 11 Counties in North Carolina have a bond rating higher than Burke County. 

- Included in the Charlotte MSA: 

   - Charlotte, NC: Aaa/AAA/AAA 

   - Mecklenburg County, NC Aaa/AAA/AAA 

   - Huntersville, NC 

   - Aaa/AAA/nr 

- Union County, NC Aaa/AA+/AA+ 

- Cabarrus County, NC Aa1/AA+/AA+ 

- Indian Trail, NC Aa1/AA+/nr 

- Matthews, NC Aa1/AA+/nr 

- York County, SC Aa1/AA+/nr 

- Burke County, NC Aa2/AA-/nr 

- Gaston County, NC Aa2/AA/nr 

- Gastonia, NC Aa2/AA-/AA 

- Mint Hill, NC Aa2/ nr /nr 

- Mooresville, NC Aa2/AA/nr 

- Mount Holly, NC Aa2/AA/nr 

- Rowan County, NC Aa2/AA-/AA+ 

- Kannapolis, NC Aa3/AA-/nr 

- Lincoln County, NC Aa3/AA+/AA+ 

- Rock Hill, SC Aa3/AA-/nr 

**Packet Pg. 381**
{16}------------------------------------------------
**3.3.b** 

CAPITAL IMPROVEMENT PLAN FY 2025-2029 

## Debt Affordability 

CAPITAL IMPROVEMENT PLAN FY 2025-2029 

Burke County’s capital improvement plan policy formally adopts several key debt management policy benchmarks that have been adopted by the Board of Commissioners.  Included in those are debt ratios that the County Manager and Finance Director are required to regularly measure and manage inside key parameters.  These benchmarks help promote strong affordability.  Several key data indicators included in the policy are: 

- 10-year payout 

- Debt Service as a percentage of total expenditures 

- Debt to assessed value 

- Minimum fund balance policy 

Over the next five (5) years, Burke County, in order to execute this CIP plan proposal, anticipates strategic debt issuances.  Both short term and long-term, major, and non-major projects are equally evaluated for the advantages of financing versus pay-as-you-go ( _of the_ **net costs** _after grant opportunities are explored_ ). 

## Conclusion 

Burke County’s capital improvement plan has two parts – a capital budget and a capital improvement plan policy (Appendix A).  The capital budget is a future focused tool that very surgically anticipates aligning available known resources with anticipated uses.  I am very pleased with the evolutionary nature of the County’s first formal CIP plan, which begins with the adoption of the 2024-2025 annual budget and is compiled based on data from the 2020 facilities assessment study and with policy direction of the Burke County Board of Commissioners.  The assessment identified priority and our staff, with the policy vision of the Board, have developed an achievable plan that leverages existing resources, does not anticipate or require a tax rate increase, and accomplishes the components of the plan over time. Within the next five (5) years, Burke County Government will have solid infrastructure across County Government for decades to come.  The space will be modern, sustainable, maintain adequate space uniformity, and be energy efficient. 

The capital improvement plan policy is a plan for capital expenditures that extend typically five years beyond the capital budget. 

The County’s capital improvement plan was developed to achieve: 

- Synchronization of future capital and operating budgets 

- Systematically evaluate competing demands for resources and aligns with funding options 

- Recognize and highlight current and future capital needs that will require future resources and prevent unexpected capital crises 

- Promote accurate and achievable long-term strategic planning 

A capital improvement plan is a dynamic community planning and fiscal management tool used to coordinate the location, timing, and financing of capital improvements over a multi-year period.  It is critically important and one of the major responsibilities for a government entity.  The CIP is a working document and should be reviewed and updated annually to reflect changing community needs, priorities, and funding opportunities to ensure that the infrastructure exists to advance strategic and long-term goals and objectives. 

**Packet Pg. 382**
{17}------------------------------------------------
**3.3.b** 

CAPITAL IMPROVEMENT PLAN FY 2025-2029 

CAPITAL IMPROVEMENT PLAN FY 2025-2029 

What is a Capital Improvement Plan? 

The capital improvement plan (CIP) outlines the County’s plans for achieving the goals, objectives, and service delivery levels desired by the Board of County Commissioners.  The purpose of this plan is to forecast and match projected revenues and major capital needs over a five (5) year period.  Capital planning is an important management tool that strengthens the linkages between community infrastructure needs and the financial capacity of the County. 

The County defines CIP capital expenditures as any expenditure of major value that recurs irregularly, results in the acquisition of a fixed asset, and has a useful life of greater than one year.  Typically, the County defines major value as an expenditure that exceeds $50,000. 

The capital improvement plan is simply that – a plan. As such, projects are subject to change based on new or shifting service needs, special financing opportunities, emergency needs, or other directives or priorities established by the Board of Commissioners. Because priorities can change, projects included in outward planning years are not guaranteed for funding.  The County CIP plan is to be updated annually to ensure that it addresses new and changing priorities within the County’s strategic plan. 

**Introduction Information** :  The introduction sections consist primarily of the Managers Message – an executive summary of the CIP from the County Manager to the Board of Commissioners. It discusses the major factors impacting the CIP and provides a summary of projects that are on the horizon as well as funding sources. 

**CIP Project Information:** This section includes a brief summary of the County’s capital improvement projects approved in the fiscal year budget. For each capital expenditure, the plan includes a description of the project, justification of expenditure and how it addresses a County strategic goal.  If applicable, the plan also addresses ongoing operational costs. 

**Development of The CIP Plan:** The CIP plan is to be updated annually during the annual budget process and is to compete against other priorities of the strategic plan.  Department Heads submit their capital planning documents in early February – which are then initially reviewed by the County budget office. 

Once the projects are evaluated, the budget office recommends the selection and timing of capital projects through future fiscal years to the County Manager. First-year projects are incorporated into the County Manager’s recommended annual operating budget. In some cases, plans are made to include the project in a separate capital project ordinance, to be approved by the Board of Commissioners when the operating budget is approved. 

**Operating Budget Impacts:** Departmental budgets may be impacted by capital projects once they are completed and require maintenance/upkeep. Examples of these impacts include additional or reduced utilities, fuel costs, or staffing changes, which may not be realized until after projects are completed. When available, the impacts of capital projects on the annual operating budget are estimated and included. For many projects, the operating costs are captured in the department’s annual operating budget and no additional operating costs are listed. Most projects will not have an operating impact in the initial funding year since this is typically the construction/installation phase and operating budgets are not impacted. 

**Packet Pg. 383**
{18}------------------------------------------------
**3.3.b** 

CAPITAL IMPROVEMENT PLAN FY 2025-2029 

CAPITAL IMPROVEMENT PLAN FY 2025-2029 

Appendix A 

Burke County Capital Improvement Plan Policy 

## **I. PREPARATION OF THE CAPITAL IMPROVEMENT PLAN (CIP):** 

- A. The purpose of the capital improvement plan (CIP) is to forecast and match projected revenues and major capital needs over a five (5)-year period. Long-range capital planning is an important management tool, which strengthens the linkages between community infrastructure needs and the financial capacity of the County. 

- B. All proposals for capital investment shall go through the capital planning process. 

- C. Definition of appropriate capital items for inclusion on the CIP: 

   1. Definition of a CIP capital expenditure – Expenditure of major value that recurs irregularly, results in the acquisition of a fixed asset, and has a useful life greater than one (1) year. 

   2. As a rule of thumb, items to be included in the CIP include those which: 

      - (a) Involve the acquisition, renovation, and/or construction of a single fixed asset greater than $50,000 – excluding vehicle or equipment purchases other than major public safety rolling stock– which are included. 

      - (b) involve any land purchases not associated with or included in another CIP project. 

- D. Difference between departmental capital outlay items (in operating budget) and capital project outlay items (in CIP): 

   1. Departmental capital items shall not be submitted as part of the CIP. Departmental capital items include: 

      - (a) Equipment/tools, furniture, office equipment such as computers and fax machines, minor remodeling, or other construction projects below $50,000 (such items should be outlined in the “Capital Outlay” section of the operating budget request). 

      - (b) all vehicles/rolling stock/machinery below $50,000 other than public safety. 

   2. However, any upcoming, or 1st year costs associated with a CIP request shall be entered in the department’s operating budget request to ensure that 1st year CIP costs are noted and included in the Manager’s Recommended Budget. 

- E. Inclusion of expenditures for maintenance and/or staffing in the CIP: 

   1. All operating, maintenance, and personnel budget expenditures associated with the purchase of a CIP item shall be included and noted in the annual operating budget. However, for reporting and future expenditure forecasting purposes, the estimated additional expenditures on operating, maintenance, and personnel shall be included on all CIP requests. 

## **II. DEVELOPMENT PROCESS:** 

- A. Departments are responsible for identifying, documenting, and justifying CIP requests. Departments are also responsible for obtaining project cost estimates and identifying appropriate revenue sources for the project (the Finance Dept. shall assist in identifying costs and appropriate revenue sources). 

- B. The County Manager, in conjunction with the Finance Director and Budget staff, shall be responsible for coordinating the CIP process and submission of the CIP to the Board of Commissioners. 

**Packet Pg. 384**
{19}------------------------------------------------
**3.3.b** 

CAPITAL IMPROVEMENT PLAN FY 2025-2029 

CAPITAL IMPROVEMENT PLAN FY 2025-2029 

## Appendix A 

- C. The Finance Director shall evaluate and recommend a ranking of proposed projects to the Manager. 

- D. Board review, recommendation, and adoption of CIP: 

   1. The County Manager’s Recommended CIP shall be submitted to the Board for their review and recommendation during the beginning stages of the annual budget process. NOTE: Governing Body recommendation of the CIP does not authorize money for any of the projects in the plan, but the recommendation by the Governing Body shall provide the County Manager direction to proceed with formulating the annual CIP and inclusion of first year CIP items in the County Manager’s Recommended County Budget. 

   2. A Capital Projects Ordinance will be adopted by County Commissioners with the County’s Operating Budget establishing necessary project fund structures for CIP expenditures at the beginning of the fiscal year. 

## **III. EVALUATION OF PROJECT MERIT:** 

- A. Proposed CIP items will be evaluated and ranked according to merit by requesting departments. B. Projects should generally be foreseen ahead of the time (preferably 2+ years) of need to allow time for planning long-term financing strategies or financing methods. 

## **IV. FUNDING SOURCES:** 

- A. Debt will be considered for capital projects under the following circumstances: 

   1. The capital item is a long-living (useful life greater than one (1) year) asset. 

   2. The asset has a useful life expectancy that equals or exceeds the length of the debt financing period. 

- B. The following types or combination of financing may be considered under the following circumstances: 

   1. Debt methods: 

      - (a) General Obligation Bonds (G.O. Bonds) – The capital item is used for a public facility or equipment that is a public good and that has no revenue-producing capability (e.g. municipal buildings or structures). Generally, G.O. Bonds are only used for major General Fund projects and require a referendum. 

      - (b) 2/3 General Obligation Bonds – Without voter approval, G.O. Bonds may be issued annually on 2/3 of net G.O. debt reduction (principal retirement) in the prior year. 

      - (c) Revenue Bonds -- The capital item is used for a non-public good in which a revenue stream is associated with the capital item (e.g. solid waste). 

      - (d) Property Secured Debt – The capital item can be secured as collateral itself. Includes lease or installment purchase transactions and certificates of participation (COPS) or limited obligation bonds (LOBS). 

   2. Non-debt methods (Also referred to as Pay-as-you-go, or Pay-Go) 

      - (a) Current revenues – The capital item can be acquired through existing revenues. 

      - (b) Capital reserves – The capital item can be funded from designated taxes or revenue streams that are set aside in a separate fund. 

      - (c) Fund Balance – The capital item can be funded with unassigned operating fund balances. (d) Grants – Funding of the capital item was secured upon application of a governmental grant. 

      - (e) Gifts – The capital item may be purchased or acquired with restricted or non- restricted donations by citizens or corporations. 

**Packet Pg. 385**
{20}------------------------------------------------
**3.3.b** 

CAPITAL IMPROVEMENT PLAN FY 2025-2029 

CAPITAL IMPROVEMENT PLAN FY 2025-2029 

- C. Debt Limits 

   1. The County shall not exceed N.C.G.S. 159-55(c) Net debt as a percentage of estimated market value of taxable property shall not exceed [2.5%].  Net debt is defined as any and all debt that is tax-supported. 

   2. The ratio of tax-supported debt service expenditures as a percent of total governmental fund expenditures shall not exceed [15.0%] with a minimum aggregate ten-year tax-supported principal payout ratio of [50%]. 

   3. The County Finance Director shall review other key debt ratios, see below, and inform the Board of Commissioners of any debt issuance/restructuring effects: 

      - (a) 10-year payout 

      - (b) Debt Service as a percentage of total expenditures 

      - (c) Debt to assessed value 

   4. “In the event that the County anticipates exceeding the policy requirements stated above, Staff may request an exception from the Board stating the reason and length of time for the exception.” 

- D. Over or Underestimated Projects 

   1. In the case of a capital project that is under or overestimated, projects will be evaluated on a case-by-case basis. 

Financing Position: 

Development of a capital improvement plan requires the alignment of an identified project need with a specific funding source.  Burke County has three primary funding sources for capital improvement projects: 

- 1.) Pay-as-you-go – operational in nature – less than $50,000, approved in budget process. 

- 2.) Capital reserve fund – funded through operational re-engineering savings to fund future projects. 

- 3.) Debt financing – Bank or public borrowing – requires L.G.C. and local Board approval. Paid back over useful life of the asset. 

“The County will coordinate development of the capital improvement budget with development of the operating budget.  Future operating costs associated with new capital improvements will be projected and included in operating budget forecasts.” 

“The County will identify the estimated costs and potential funding sources for each capital project proposal before it is submitted for approval and maintain a balanced CIP with identified funding sources for proposed project expenses.” 