**LAKESHORE VILLAS PROJECT UPDATE** 

- **Current AHSP Bond Fund Allocation:** $3,318,616 Loan 

   - Project Cost Increases: $40,534,303 (previously $39,288,315) 

   - Could not apply for unallocated HOME Funding in the last 4 months 

   - Increased Deferred Developer Fee to $620,929, but still experiencing a remaining funding gap of $299,702 

   - Project Timeline impacted by HUD Environmental Assessment and U.S. Army Corps of Engineers General Permit 

      - “…To avoid potential effects to federally endangered species, tree clearing on the site should only occur between October 15, 2023 and March 31, 2024.” (USACE) 

**Potential Solution:** The Affordable Housing Subcommittee recommended increasing the allocation of Bond Proceeds to fill their funding gap.