# MINUTES City Council Public Works & Utilities Committee 

Wednesday, February 4, 2026 - 3:30 p.m. City Council Chambers 

Members Present: Lauren Wise, Chair, Council Member Owen Carson, Citizen Member Mayor Maureen Copelof, Ex-Officio 

Staff Present: David Todd, Assistant City Manager Dennis Richardson, Water Treatment Plant Supervisor Aaron Winans, Wastewater Treatment Plant Superintendent Shawnee Cummings, Assistant to the City Manager 

Guests: 

Harvey Sankey 

Media: n/a 

## A. Welcome and Call to Order 

Committee Chair Lauren Wise called the meeting to order at 3:34 p.m. 

## B. Certification of Quorum 

Assistant to the City Manager Shawnee Cummings certified that a quorum was present. 

## C. Approval of Agenda 

Mr. Carson moved, seconded by Mr. Wise to approve the agenda as presented. The motion carried unanimously. 

## D. Approval of Minutes - January 7, 2026 Meeting 

Mr. Carson moved, seconded by Mr. Wise to approve the minutes of the January 7, 2026 meeting as presented. The motion carried unanimously. 

## E. Norton Creek Restoration Phases 2 and 3 

After additional discussion, this item was removed from the agenda and will be discussed at the next Committee meeting. 

## F. Project Updates - Mr. Todd presented the following updates: 

## 1. Public Works Update 


{2}------------------------------------------------
## Mr. Todd compiled a list of updates on work performed by Public Works employees in the past 30 days, outside of their normal scope of work and day-to-day responsibilities. 

Water and Sewer Fixed 21 water leaks Repaired/Unstopped 12 sewer lines Made 6 water and sewer taps Assisted with plowing and satting roads 

Streets Poured 5 yards of concrete for sidewalk repairs Installed 6 new stop signs Instatled 6 new traffic pattern ahead signs Installed 3 stop sign ahead signs Installed 6 yellow flashing tights installed 9 red flashing lights Repainted two stop bars Collected 30 small dump truckloads of brush Collected 20 large brush truckloads of brush Used 10 yards of cold patch in Straus Park on edge of rods and potholes Used 5 yards of cold patch for potholes and utility cuts Cleaned up storm debris on roads from ice storm Chainsaw/tree cutting safety class, Tannery North Trail Construction Formed 80 ft of concrete for curb on Railroad Avenue Plowed snow for snowstorm Put 10 buckets of ice mett on handicap ramps for ice storm Put 15 buckets of ice melt on handicap ramps for snowstorm Prepared trucks and equipment for ice and snowstorm Assisted with water leaks and sewer blockages Building and Grounds Completed 25 Non-Routine Work Orders installed signs and lights at McLean and Railroad trail crossing, truncated domes yet to be installed Fleet Maintenance Completed 246 Work Orders 

## Z. Stormwater Master Plan 

McAdams is contracted for the Citywide Stormwater Master Plan and is currently advancing Phase1 of the project, mainly focusing on Existing Conditions Analysis. This effort is supported by desktop analysis, geodatabase development and management, analysis of existing stormwater systems, and preliminary CIP prioritization planning. 

The field data collection task is approximately 95% complete, with activities concluded on January 8, 2026. Additional field data collection may be required after CCTV and analysis of existing stormwater systems is completed. CCTV services will begin on February 9, 2026 and will conclude in late March. 

Minutes — Council Public Works and Utilities Committee Meeting — February 4, 2026 Page 2 of 9 


{3}------------------------------------------------
Below is the overall schedule: 

1. Overall Project Schedule and Scope: a. Phase 1 completed in fiscal year 2026 (June 2025 - June 2026) i. Identification of Projects and Capital Improvement Planning 1. October - January: Field work and post processing of data a. Initial field data collection completed early January. 2. January: Start coordination with CCTV a. CCTV to begin 02/09 for one week. CCTV to conclude in late March with 1.5 weeks of work. CCTV data to be provided in May 2026. 

3. January: Start building H+H models 4. January (01/15): Stormwater UDO Kickoff a. Next scheduled meeting on 02/17 to discuss action items. 

5. February - April: CCTV crews on-site a. Week of 02/09 + late March. 6. April: Final field visits for any missing data 7. February - April: Finalizing existing conditions models + Prioritization 

8. April-June: Report writing + finalizing deliverables b. Phase 2 completed in fiscal year 2027 (July 2026 - June 2027) i. Schematic Design and Identification of Funding 

## 3. Hillview Street Culvert 

We are finalizing the plans this week and procurement specs. Copies of both items will be provided for review later this week. 

Hillview St. Culvert rcs 

**==> picture [459 x 217] intentionally omitted <==**

**----- Start of picture text -----**<br>
City of Brevard, NC Display week:<br>_ Nou Ze | Dec tates | JanS.2tes | [Feb2,2005] | Mar 2006 | Agee.2008 | Mage.200e| Maythzees | Math 2026<br>Eristing Conditions Investigation<br>Petite<br>Total wes wewzs i<br>Final Design Phase<br>Tota wanes WR<br>Permitting Services |<br>Toul was 26 |<br>Issue for Bidding<br>Svweek td petiod = wees art ae<br>ominton<br>S om Vee<br>**----- End of picture text -----**<br>


Minutes — Council Public Works and Utilities Committee Meeting — February 4, 2026 Page 3 of 9 


{4}------------------------------------------------
## 4. Water Treatment Plant Renovation 

## Work to date: 

1. New Clearwell top completed, poured. Waiting on concrete testing reports. 

2. Starting installation(s) of the new actuators. 

3. Old (blue) control panel - removed, fabrication of new desktop for that old location. 

4. Working on final approval for new pumps in pump room. There were specific design loads to consider for a new connection to existing concrete flooring. 

5. Generator Pad is under construction, formwork to start and concrete poured. 6. New Generator is arriving at the end of February. 

## Upcoming work: Work over the next couple of months 

1. Complete Clearwell work and tank testing. 

2. Estimated delivery time for Back Up Power generator is 2/27/2026. 

3. Estimated delivery time for automatic transfer switch is 3/12/2026. 

4. Continued work on changing out the actuators. 5. New Filter Media is on for the first week of March. 6. Clean flocculators week of February 16th so that the metal fabricators can start installation work. 

**==> picture [411 x 122] intentionally omitted <==**

**----- Start of picture text -----**<br>
City of Brevard - Water Treatment Plant Improvements :<br>NCDEQ SRP-D-ARP-0222<br>BrownPA - 20042<br>wea<7Por aoe nary aaa TD<br>[ProjectAdvertiselGidMarch25,2025 pt T yeet e eeeeeeeeeeeee<br>JRE-BidAprit36,2025 0<br>\4/29/2025-NCDEQBIDpackageforApproval<br>May29,20225NCDEQATAletterreceived|| ||<br>NoticeotAwardreceived<br>May 30,2025 || | | mm TT TT<br>ExecuteContract-NaticectoPraceed<br>[JuneConsruction3esDays 10,2025 |||||| || mT{| | TT Tj<br>**----- End of picture text -----**<br>


## 5. Water and Sewer Asset Inventory Assessment 

a. Water System Asset Inventory & Assessment 

Field Work to Date: 

- e Completed with the exception of the missing items to be located by City Staff 

Current Status: 

- e Model has been constructed and items identified e Awaiting PRV information from the City 

- e Flow tests have been completed 

Minutes — Council Public Works and Utilities Committee Meeting — February 4, 2026 Page 4 of 9 


{5}------------------------------------------------
- e System partially calibrated 

- e Awaiting future demand (upcoming development) information 

- « Completed recommended improvements based on failing infrastructure e On-site inspection and assessment of the existing pump stations completed « Demand projections based on information provided Planning Department completed e Preparation of a proposed improvements program based on future demand 

## Next Steps: 

- e Finalize Report. 

## Schedule of Remaining Tasks: 

**==> picture [426 x 194] intentionally omitted <==**

**----- Start of picture text -----**<br>
||||||
|---|---|---|---|---|
|Task|Completion Date|
|Field Work (not including|missing items)|completed|
|Initial|Model|(for calibration)|completed|
|Flow Tests (by City of Brevard)|completed|
|Analysis of Ex. Water System|completed|
|Update Demand Projections with regard to TAZ data|completed|
|Demand Projections based on upcoming development|completed|
|Capital Improvements|Program & Financial Impact|completed|
|February|13, 2026 - mailing|
|Project|Close|out|deliverables|next week|

**----- End of picture text -----**<br>


## b. Sewer System Asset Inventory & Assessment 

Current Status: 

- e Fieldwork is 100% complete 

- e Sewer mapping is 100% complete 

- e Preparing an infrastructure replacement program 

- e Demand projections based on NCDOT TAZ 

- e Demand projections based on information provided by Planning Department completed 

Next Steps: 

- e Identify and rate critical infrastructure 

- e Preparation of a proposed improvements program based on demand projections 

Schedule of Remaining Tasks: 

Minutes — Council Public Works and Utilities Committee Meeting — February 4, 2026 Page 5 of 9 


{6}------------------------------------------------
|Task|CompletionDate||
|---|---|---|
|:<br>:<br>.<br>wee<br>FieldWork(not includingmissingitems)|‘Completed~additional<br>manholebeinglocated||<br>||
|SmokeTestingofKingsCreekBasin|completed||
|Identifyand Rate Critical Infrastructure|TBD||
|Update Demand Projections|completed||
|IdentifyAreas:NeedingSewerwith Planning Dept.|completed||
|Update Existing InfrastructureAssessment|completed||
|Capital Improvements Program - Failing Infrastructure|completed||
|Capital Improvements Program - Future Development|completed||
|Financial Impact|completed||
|Presentto CityofBrevard|TBD||
||Completed - Deliverables||
|Project Close-out|shallbe delivered Feb. 5,||
|||2026||



## 6. Gallimore Sewer Rehab Update 

## Gallimore Basin Sewer Rehab Change Order #2 

- e The pipe lining along County Club Road and Caldwell Street is complete. e The manholes along Country Club Road and Caldwell Street are complete. e BLD has lined the service laterals along Caldwell and Country Club Rd. 

- e The Contractor is currently negotiating with a Sub to perform point repairs along England St and install cleanouts. 

- e Contractor is overdue in providing an updated schedule. ¢ Contractor expected to be on site to line England St the week ofFebruary 9, 2026. 

**==> picture [529 x 106] intentionally omitted <==**

**----- Start of picture text -----**<br>
mai<br>ip m=.<br>i<br>Aap _ | eon |<br>| ee ee Cd<br>PLOL Lo AAG IID OOPS ISI LOPPEOED LP LIE PD ALS LP PP OID GAGS AL LS |<br>**----- End of picture text -----**<br>


## 7. Sewer Lift Station Rehabilitation Project 

The Pump Station Rehab and Replacement project Contract has been executed, and a preconstruction meeting was held on 6/30/25. 

Minutes — Council Public Works and Utilities Committee Meeting — February 4, 2026 Page 6 of 9 


{7}------------------------------------------------
## TP Howard is currently mobilized at the Gallimore Pump Station. 

- e Slide rail system has been installed, and the contractor has started to install the pump station wet well. 

Shop drawings and submittals are continuing to be reviewed. 

## Change Order No. 1 (Grinder Vault) 

e Contractor has been sent final Change Order and received approval for associated grinder vault shop drawing. 

Progress has been made on both the Fish Camp and Gallimore Road easements. Terms have been reached and staff are currently finalizing paperwork. 

## Sewer Pump Station Rehab Project 

|sexe<br>“i rnin a<br>Wen<br>Task<br>Hut_Jaug [Sep|Oct [Nov/Dec [ian |Feb[Mar|Apr [May]Jun[dut_[Aug|Sep|Oct [Nov|Dec an[Feb[Mar]<br>GallimorePumpStation(12/5/25-7/3/26)<br>||tf<br>| |<br>|<br>{| [|EE<br>FishCampPumpStation (5/14/28-8/28/26) t+Tf tt<br>| ft ity<br>yiisonPumpStation<br>(2/2 5/26)<br>PT Tt TT tt<br>BEER<br>PunchOut&Cleanup(8/14/26-10/2/26<br>fr } ty<br>fy<br>rT | tt tt]<br>||P||<br>ARPAFundingDeadline (December31,2026<br>|<br>|<br>|<br>rT Tt TTT<br>T || fis| | |<br>cors-rnatcompetonoaeizen<br>|||||||<br>|<br>|<br>|<br>Ti)<br>|<br>|TTT|<br>|<br>kL||
|---|



## 8. WWTP Renovation and Upgrade Project 

The City is still waiting on the Letter of Intent to Fund for the funding the City received after Hurricane Helene, which will outline the next steps required for this funding. We anticipate that next steps will include an Engineer’s Report and Plan and Bidding document approval. 

KCI was able to determine that the HMGP advanced assistance program, which does not allow for partial funding of a project, would not be able to fund the design and construction of the Phase 2 improvements based upon the preliminary BCA prepared by ICF. KCI will continue to evaluate other alternatives for funding the Phase 2 improvements. 

KCI is continuing to work on the 60% design of Phase 1 and PER. Over the coming weeks KC] will be onsite with a potential contractor to review the site and discuss the site plans for the Phase 1 design with the WWTP staff. We also anticipate scheduling a funding meeting to discuss alternatives for funding Phase 2. 

Minutes — Council Public Works and Utilities Committee Meeting — February 4, 2026 Page 7 of 9 


{8}------------------------------------------------
**==> picture [502 x 250] intentionally omitted <==**

**----- Start of picture text -----**<br>
ee FY FF FY FF FP PP YP FF FF PP<br>a a Sse ece——e = ee<br>Os ee EEE SS SS i eee SS SS SS SS SSS SPSS SSS Ew eee ee ee So<br>< epee Palme Pye oT oy whee<br>reme| ___veecawnon | uration |oo an |r| tar] ne [tay] sn] et || 0p] Ont | ee] ve | Jon | er | [rey | Jot]m7 ang<br>[Proposed Schege eee<br>—<br>SE sr<br>— oe<br>SNee<br>oe<br>[10 | rea Fiaving Apgtcaten «do eo<br>[14]eee& Conewurton 28 Mon = Aa a ee<br>Phase I - Future Upgrade (TSO) SS SS A SS A<br>eSBiting —— SS SS SS<br>**----- End of picture text -----**<br>


**==> picture [109 x 10] intentionally omitted <==**

**----- Start of picture text -----**<br>
9. Public Comment<br>**----- End of picture text -----**<br>


Harvey Sankey asked if enough overtime was budgeted to cover the Public Works employees who worked during Winter Storms Fern and Gianna. Mr. Richardson stated that the City does include sufficient overtime in its budget. 

Harvey Sankey also inquired as to communications and how to best highlight the information in the Public Works Update. Mayor Copelof stated that the City has been consistently sharing information on social media and has posts dedicated to Public Works. Councilmember Wise stated that between the Public Works & Utilities Committee meetings, Committee meeting minutes, City Council meetings, City Council meeting minutes, social media, a communications coordinator, newsletters, Meet the Mayor events, and making staff and elected officials available to constituents, there are ten different ways to obtain this information. Councilmember Wise added that he agrees that communication related to the City’s work is important, but that the information is available. Mr. Carson added that most people get their information and/or news from Facebook and that maybe placinga link to the minutes and information for the next Committee meeting on the bottom of Public Works posts would help direct citizens to the available information. 

Harvey Sankey asked if he missed an update on the Brushy Creek Sewer Rehab project, to which Mr. Todd stated that he did not include an update in his presentation, but that we are waiting for the next steps for the grant to start design work. 

Harvey Sankey also inquired about the grant for the WWTP, to which Mr. Todd stated that we were not successful in obtaining the HMGP grant. Mr. Todd added that we 

Minutes — Council Public Works and Utilities Committee Meeting — February 4, 2026 Page 8 of 9 


{9}------------------------------------------------
believe we have been awarded a State Revolving Fund loan that is a principal forgiveness loan for $5 million. The $5 million loan in combination with $8 million left of State Appropriation funds, leaves us with $13 million to cover the estimated construction costs for Phase 1. Design for Phase 1 has already been paid for. 

## 10. Set Next Meeting - March 4, 2026 at 3:30pm 

The next regular meeting of the committee will be on March 4, 2026 at 3:30pm. 

## 11. Adjourn 

There being no further business, the meeting was adjourned at 5:01 p.m. 

## Minutes Approved: March 4, 2026 