# MINUTES City Council Public Works & Utilities Committee 

# Wednesday, July 1, 2026 - 3:30 p.m. City Council Chambers 

Members Present: Lauren Wise, Chair, Council Member Gary Daniel, Vice Chair, Council Member Owen Carson, Citizen Member Mayor Maureen Copelof, Ex-Officio 

Staff Present: Wilson Hooper, City Manager David Todd, Assistant City Manager Wesley Shook, Public Works Director Dennis Richardson, Water Treatment Plant Supervisor Aaron Winans, Wastewater Treatment Plant Supervisor Becky McCann, Communications Coordinator Shawnee Cummings, Assistant to the City Manager 

Guests: Harvey Sankey 

Media: Jonathan Rich 

## A. Welcome and Call to Order 

Committee Chair Lauren Wise called the meeting to order at 3:30 p.m. 

## B. Certification of Quorum 

Assistant to the City Manager Shawnee Cummings certified that a quorum was present. 

## C. Approval of Agenda 

Mr. Carson moved, seconded by Mr. Daniel to approve the agenda as presented. The motion carried unanimously. 

## D. Approval of Minutes - June 3, 2026 Meeting 

Mr. Daniel moved, seconded by Mr. Carson to approve the minutes of the June 3, 2026 meeting as presented. The motion carried unanimously. 

## E. Project Updates - Mr. Todd presented the following updates: 

## 1. Public Works Update 


{2}------------------------------------------------
Mr. Todd compiled a list of updates on work performed by Public Works employees in the past 30 days, outside of their normal scope of work and day-to-day responsibilities. Water 

Leak Checks, Searches and/or Repairs: 10 New Lines Installed: 4 CommercialTaps: 2 Residential Taps: 1 Meter Box Replacement: 2 Meter Check or Repair: 2 Meter Replacement: 1 Hydrant Repair: 1 Chlorinating: Chlorinated 2200’ of new 10", 6" and 8” water main at the roundabout (Asheville Highway and 276}. After, made 10" water tap for new water tine project and dechtorinated 2200’ of 10”, 6” and &” water line. Completed training on the new vacuum truck. Streets Assist: fT Sanitation Assist: 1 Sewer Assist: 7 

## Sewer 

Lift Stations: Checked pump run times, inspected wet wells, pulled and cleaned out pumps, mowed and weedeated, used new vac truck to suck up all the grease built up inside wet wells. Taps: Instalied + new residential tap. Locates: 350 (as of 6/26/26}. Meetings: Met several times with contractors and customers. Trained on new Vac Truck. Line Cleaning: 5,024 feet (as of 6/26/26). Required Footage for 2026: 31,680 feet; Cleaned to Date: 38,385 feet. Exceeded requirement by 6,705 feet to date. Video Inspections: 4,722 feet (as of 6/26/26). Streets Assist: 6 (cardboard, recycling and brush collection, street repairs). Water Assist: 6 (meter replacement, feak checks, replacement of[service][lines).] 

## Streets & Sanitation 

Concrete: Dug out, hand mixed and poured, backfilled, seeded and strawed 40’ of sidewalk, 

Cold Patch: 10 potholes and 1 utility cut (20’ x 6"} and leveled up this cut. Grass Cutting: 9 utility strips, flail mowed 7 roads and trimmed grass and weeds at 25 stops, street and speed limit signs. 

Stop Signs: Moved 2 on Probart Street at Railroad Avenue. 

Painting: 4 stop bars and 1 crosswalk. 

Brush Collection: Retrieved 30 small loads of brush, 5 targe loads of brush and 40 bags of brush, 

Trash Cotlection: 217.3 tons. 

Recycle Collection: Residential- 31 tons; Commercial— 15.5 tons. Cardboard Collection: 14.9 tons. 

Special Waste Pick Up: 17 loads. Banners: Put up 4 large banners and 20 small banners. Water Assist: 2 leaks. 

## Garage 

Completed 177 fleet maintenance work orders as of 6/24. 

Minutes — Council Public Works and Utilities Committee Meeting — July 1, 2026 Page 2 of 14 


{3}------------------------------------------------
## Building & Grounds 

Mowing: Weekly, mowed 36 acres of parks and properties and bike paths. Sports Complex: Nail, light drag and lined fields for littte league {regular season and currently All-Stars). Dog Park: Replaced yard hydrant. Repairs: Small engines repaired and maintained. Train Depot: Cleared several toilet clogs and sewer. Police Department: Painted offices. Hap Simpson Park: Painted signs. City Hall: Completed ALL work orders {set up for meetings, etc.). Streets Assist: Helped to hang banners on poles downtown. 

## 2. Stormwater Master Plan 

McAdanzs is contracted for the Citywide Stormwater Master Plan and recently completed Phase1 of the project, which focused on Existing Conditions Analysis. This effort is supported by desktop analysis, geodatabase development and management, analysis of existing stormwater systems, preliminary CIP prioritization planning, and UDO updates. 

A draft report was submitted to the City at the end of June to complete Phase 1. This included existing conditions hydraulic modeling results, CIP prioritization, the UDO updates, CCTV reports, and a GIS geodatabase compiling stormwater inventory from Land of Sky and McAdams data collection. 

## Below is the schedule: 

1. Phase 2 completed in fiscal year 2027 (July 2026 —- June 2027) a. Schematic Design and Identification of Funding b. Kickoff for Phase 2 will be in July 2026 

Distribution of pipe material and diameter found in field investigations (left) and distribution of structure type and depth found in field investigations (right) are detailed in the charts below. 

**==> picture [467 x 145] intentionally omitted <==**

**----- Start of picture text -----**<br>
Pipe Material Structure Type<br>CouldNot Determine | 3 | CouldNot Determine J 1<br>7 vcp a 7 i Yardiniet-Open Throat HJ 13<br>8 AC?pvc JlTY15 153 z£ Yad nietManhole -Cx BETT17 £9<br>fb HOPE J ii S Curbinet-Open Throat Hh 4<br>= & Curbintet- Grate Ey 35<br>DIP BB. a<br>Curb intet - Combination $6<br>Che 89 cco. TT 42<br>eo i 100 Hog 200 a 2 206400—Ct—iwsiaitiaCDD<br>NUMBER OF PIPES NUMBEROF STRUCTURES<br>Figure 4:Distributionof pipe materials caltected Figure 6: Distribution of structure types collected<br>**----- End of picture text -----**<br>


Minutes — Council Public Works and Utilities Committee Meeting — July 1, 2026 Page 3 of 14 


{4}------------------------------------------------
**==> picture [471 x 610] intentionally omitted <==**

**----- Start of picture text -----**<br>
Pipe Diameter (in) Structure Depth (ft)<br>Could Not Determine60 mm14 6 | \| | ii CouldNorDeternine BE) s<br>453 | e<br>z 2 —_ ry | FS SU | 2<br>5 30 eemeres 21 wi<br>= 24 63 w 51-3 EE 37<br>3 1S es 67 | 2<br>& 4 ————"—-- z 2S TTT 105<br>a 2 ee) 68 =<br>10 =EEIWE iG a<br>48 aftteem 11:\ | | 0)ns 109<br>0 20 40 60 80 00 120 a 20 40 60 80 100 420<br>NUMBER OF PIPES NUMBER OF STRUCTURES<br>Figure 5: Distribution of pipe diemeters collected Figure 7: Distributionof structure depths collected<br>Overview of CIP prioritization matrix and project priority ranking were also provided.<br>| Prioritization Matrix<br>| 10<br>> Chery Street<br>. Neighborhood<br>iz Ducks Drive " 7<br>. Neighborhood Sitversteen Drive Cutvert<br>:<br>ten iL. | Oakwood Drive<br>io] { =<br>9 = al: j<br>e ) jan<br>x 3 = at SSS =<br>2 . ta —<br>al : = Le<br>1 ee<br>0 ! — —<br>fr) 1 2 3 4 5 6 7 8 9 10<br>Consequence of Failure<br>~ —<br>Figure 1: Prioritization Matrix PWS Results<br>Table 7: Prioritization scoring overview<br>Hot Spot Area Total Score Priority Ranking<br>GhenryStreetNeighbornood | [87S]<br>Silversteen Drive Culvert a Sor a a<br>Oakwood DriveNelghborhood | 78 ~(| [OS]<br>Batson Road Culvert<br>Oakdale Street 72 |e<br>44 Maple Street a LS) ae<br>Ducks Drive Neighborhood | 7.1 «10<br>**----- End of picture text -----**<br>


Minutes — Council Public Works and Utilities Committee Meeting — July 1, 2026 Page 4 of 14 


{5}------------------------------------------------
## 3. Hillview Street Culvert 

- © The Contractor provided an initial proposal for an alternative pump around scenario that has been reviewed and returned with questions for added detail. This alternative has not been approved by the engineer. 

- e The schedule for road closures remains as noted in email of 6/24: o Cashier's valley road from 6/26/2026 through 7/2/2023 

   - Assuming all goes good next week, both roads will remain open the week of 7/6/2026. 

   - Assume Hillview closed 7/13-20//26 through 8/7/2026. (contingent upon when our culvert hits the job). 

   - Assume Cashiers Valley closed 8/10/2026 - 9/4/2026. 

- e The Job General Superintendent is Clayton Hensley. 

- e Correspondence on 6/16 indicated that materials would begin being delivered on 6/19, including traffic control signage, which will initially be bagged (i.e., covered) until it is ready to be made active. 

- e CADD files were shared with the Contractor on 6/16/26. e WSP coordinated with NCDEQ regarding the alternative bypass option and confirmed that it is allowable as long as the construction does not extend beyond the approved area. This discussion preceded the current discussion regarding the alternative pump-around scenario, which has not been approved. 

- e Submittal #1 was approved with comments on 5/27/26. 

**==> picture [178 x 14] intentionally omitted <==**

**----- Start of picture text -----**<br>
Hillview St. Culvert<br>**----- End of picture text -----**<br>


**==> picture [443 x 219] intentionally omitted <==**

**----- Start of picture text -----**<br>
Cityof Brevard, NC<br>Tas paoanesa tant ew . MayEET4, 2026 eta-_Teat Jun eTeTa1, 2028 eter eralPRE eeTet a feta,  TeTeTe9 3, 2028.Tats ats=  ToT931, Te 226 eT<br>Tots 100% TAR 11/24/25<br>Final Design Phase<br>Permitting Services<br>4 week bid period 100% 2/20/26 324128<br>Gem<br>Closa-out na M1726 B31/26 a<br>v ~ a nm Se<br>Se Pole<br>**----- End of picture text -----**<br>


Minutes — Council Public Works and Utilities Committee Meeting ~ July 1, 2026 Page 5 of 14 


{6}------------------------------------------------
## 4. Water Treatment Plant Renovation 

## Work to date: 

1. New Clearwell has been disinfected and passed its leakage test (dropped zero inches in 24 hours’ time.), in use, and backfill has been started with clean stone. 

2. All of the new actuators have been installed. 3. Conduit work and new control panel work continues in the Pump room. See attached. 

4. The installation of the equipment in the flocculation basin is completed. 

Upcoming work: Work over the next couple of months 

**==> picture [395 x 124] intentionally omitted <==**

**----- Start of picture text -----**<br>
1. Delivery of new pumps in August for installation<br>City of Brevard - Water Treatment Plant Improvements :<br>NEDEQ SAP-D-ARP.0222<br>Pee Ps x ig go tas aago<br>[Project Advertise ‘ i — = = | 7 | |<br>5 ——<br>RE-Bid April 15, 2025 : z g | | [| |<br>Se<br>**----- End of picture text -----**<br>


5. Gallimore Sewer Rehab Update 

## Gallimore Basin Sewer Rehab Change Order #2 

- e The Contractor is currently negotiating with a Sub to perform point repairs along England St and install cleanouts. 

- e Contractor is overdue in providing an updated schedule. e 3 sewer services along Caldwell St remain to be lined after point repairs. ¢« 3-services along England Street to be lined. e 10cleanouts to be installed. e Contractor waiting on Sub to schedule excavation and repair of existing services and installation of cleanouts. 

- e Contractor appears to be attempting to forgo the repair of the services mentioned above, citing a lack of sub-contractor interest in performing the necessary point repairs. No updated schedule has been provided for this work. 

- e The Contractor would like to schedule a Teams meeting with the City to discuss closing the project. 

- e Payment Application #10 remains on hold 

Minutes — Council Public Works and Utilities Committee Meeting —July 1, 2026 Page 6 of 14 


{7}------------------------------------------------
**==> picture [290 x 23] intentionally omitted <==**

**----- Start of picture text -----**<br>
ty a eer<br>att ||<br>**----- End of picture text -----**<br>


## 6. Sewer Pump Station Rehabilitation Project 

## Gallimore Road Site 

- e TP Howard has installed the pump station wet well, grinder vault, meter and valve vaults and has installed the piping between the vaults. 

- e Site grading has been completed up to side grade to include the removal of unsuitable soils and import of new material under guidance from BLE. 

- e Creek crossing with the gravity sewer and force main is nearing completion. ¢ Electrical work has commenced and is the current critical path to activation. e The contractor has completed the majority of the installation of the gravity sewer and manholes between the new pump station and the existing pump station. 

## Wilson Road Site 

- e TPH has installed the new natural gas generator and completed the piping of the gas service to the generator. 

- e Enbridge has relocated the gas service meter and will be inspecting the service to activate the generator. 

- ¢ Generator startup and training should occur in July 2026. 

## Fish Camp Site 

- e TPH has mobilized to the site and installed erosion control measures and set up the temporary bypass pumps to allow rehabilitation work to commence. 

- e New vaive vault and piping is being installed as well as initial work to install new pumps in the wet well. 

## General 

- e Shop drawings and submittals are winding down; all major equipment has been approved. 

- e Both the Fish Camp and Gallimore Road easements have been finalized, and the paperwork is now complete. 

Minutes — Council Public Works and Utilities Committee Meeting — July 1, 2026 Page 7 of 14 


{8}------------------------------------------------
**==> picture [445 x 621] intentionally omitted <==**

**----- Start of picture text -----**<br>
Sewer Pump Station Rehab Project<br>| nuaTask jut_[augia Tag |Sep2 [OctTos[Nov [Declanpectin [ab|Feb [Maran aor[Apr Tovlc [Mayliun [JtPor Tae[Aug|Sep|[ben Tae Oct [Nov|Dec|iannovlnestion [Febec [Mar<br>atimorerumpstatoniizsnszisz) ||| | mt ttt<br>Funcomprumpsiaionsareasues)wusonrumpsiatoncsas-sa)Purchourscicanuprrarzossaez ||_|| || || || || || || || | Pt [PT] Pt tTtttT<br>pevewaesonmmowenmrnongcon-rinatcompiaionareewrren|_|LF |Lt| | |LY| |LL| | |LP| |EL| tt tta<br>| | | | | | | | | | | |] | | | | TT | a]<br>7. WWTP Renovation and Upgrade Project<br>KCI is continuing to work with their subconsultants to finalize the plans and<br>specifications, while simultaneously wrapping up the permitting and funding<br>approval process necessary for the bidding of the Phase 1 design over the next<br>several weeks. The recently awarded $5M supplemental Helene Funding required<br>preparation and submittal of an Engineering Report and Environmental Information<br>Document (ER-EID). This ER-EID was uploaded to the State’s electronic permit<br>portal on June 24* for state review and approval. KCI is targeting mid-July to submit<br>Construction Plans and Specs to NCDEQ for review and approval.<br>KCI has discussed with with Brevard staff pursuing FEMA BRIC pursuing FEMA BRIC FEMA BRIC BRIC funding for Phase 2 but this<br>funding will be will be be limited to site and and chlorine contact basin basin improvements. KCI will<br>continue to work with work with with the City staff on pursuing Phase on pursuing Phase pursuing Phase Phase 2 funding.<br>The Basin study performed by KCI has been updated performed by KCI has been updated by KCI has been updated KCI has been updated been updated updated to include the expected flows<br>the Davidson River Village and Village and and is being internally being internally internally reviewed. An An updated PowerPoint and<br>figures will be provided to Brevard staff for review. for review. review.<br>SREVARD WWTP PER/PHASE 1 & 2UPGRADE DESIGN- ESTIMATED PROJECT SCHEDULE clA KCIseat as |S amyTECHNOLOGIES TSCA cee siepc an MeL<br>frewe|______vescrnon| oaraton_|ay] in| ave S| ont | tw|| an] re | ar] Ar] zy | |<br>[1 | Phase |-Hesiwotts and Age Prime a SS ee SS SS Se SE Sa<br>—————seg «de —SS a<br>[4 | "Helene Funding Enghesring Repat@ Approval [2M | a<br>[6 | Bietng Tuned a<br>aa CFL Sel St [eS<br>Preliminey Design Start Date TBD) 6iton<br>—————[8 |" Bissing & Constudion<br>eee[| — 2ohon ——— ee<br>a F r rangeaatinese ft - Future Upgrade (TED)SYi==<br>jreme|_vencrrrmw ____| untangle |] on] [av | ron sn ron mr] ea |] ex] ot mer owes v0 oe] oe<br>ee eee 22 a an ee ee ee i<br>**----- End of picture text -----**<br>


KCI has discussed with with Brevard staff pursuing FEMA BRIC pursuing FEMA BRIC FEMA BRIC BRIC funding for Phase 2 but this funding will be will be be limited to site and and chlorine contact basin basin improvements. KCI will continue to work with work with with the City staff on pursuing Phase on pursuing Phase pursuing Phase Phase 2 funding. 

The Basin study performed by KCI has been updated performed by KCI has been updated by KCI has been updated KCI has been updated been updated updated to include the expected flows from the Davidson River Village and Village and and is being internally being internally internally reviewed. An An updated PowerPoint and figures will be provided to Brevard staff for review. for review. review. 

Minutes — Council Public Works and Utilities Committee Meeting — July 1, 2026 Page 8 of 14 


{9}------------------------------------------------
## 8. Tannery Smokestack 

D.H. Griffin has been awarded the contract to remove both the underground vault and smokestack. The contract was revised to include saving 10 pallets of bricks for use on a future project. D.H. Griffin has ordered the needed geotextile materials and are on hold to start work pending approval of the Environmental Management Plan (EMP) by DEQ. 

Our engineer has submitted both the EMP for the vault and the smokestack to DEQ and we are currently awaiting DEQ approval. Initial estimates were as long as 2 months to approve the EMPs. Staff have been working with DEQ in advance of the submittals in hopes of greasing the rails for quicker approval. 

Demolition, once started, is estimated to take about a month to complete for the smokestack and a couple of weeks for the vault. 

- F. Fats, Oils, and Grease (FOG) Code Changes 

Mr. Hooper said the FOG program is a service level change in the budget, but it did not get much attention as it was relatively inexpensive. The service level change will be in how we operate and how the rules require businesses to operate. This change to our services was mandated by the State and was something the City had to do. 

Mr. Todd gave a presentation (Attachment A) on fats, oils, and grease, and the major changes to the FOG program. When FOG enters the wastewater system, it collects on the top, causes blockages to form in the system, and prevents floats from working properly. Blockages can also result in sanitary sewer overflows. 

The FOG program has botha residential and a commercial component. For residents, it is critical that households do not put fats, oil, and grease down the drain. For commercial businesses, particularly food service establishments (FSE), they will need to use an interceptor or grease trap to catch grease that enters the system. Routine maintenance will involve a company that needs to clean the grease trap and dispose of the FOG somewhere other than in the City’s wastewater system. Companies in Asheville and Knoxville can use the harvested FOG to make biodiesel. 

Mr. Todd explained that we are updating our FOG program because our permit says we must develop and implement an enforceable program, in which the City can take action against users who have not properly installed, operated, and maintained their grease traps or interceptors, or otherwise violated the terms of the enforcement program. In April of 2025, NCDEQ also issued a compliance finding indicating that the City’s FOG program is not enforceable, and that the City’s Sewer Use Ordinance allows the City to take action against violators who introduce prohibited substances into the collection system. NCDEQ’s finding further advised the City to establish a method for documenting and checking non-residential user compliance. 

> Minutes — Council Public Works and Utilities Committee Meeting — July 1, 2026 Page 9 of 14 


{10}------------------------------------------------
Mr. Todd said the City’s UDO is silent on FOG, but the Code of Ordinances has a paragraph stating that any water or waste containing fats, wax, grease, or oil in excess of 100 mg/L is a restricted discharge. Mr. Todd also outlined other sections in the Code of Ordinances where it states that viscous substances, grease, and fatty materials are prohibited. Mr. Carson asked if customers will know how much 100 mg/L is. Mr. Todd said no, but ultimately they will be looking for compliance, which involves a functioning and maintained grease interceptor. Mr. Winans added that it also varies with the amount of wastewater discharged. Mr. Todd said that if 100 mg/L was changed to 0, it would be a prohibited discharge and that is not practical. Mr. Daniel asked if testing is performed at the plant. Mr. Winans said yes, which indicates how much FOG is in the entire system, and he also tests at lift stations. 

Mr. Todd said our current FOG program consists of education and outreach, which is on the City’s website. In the past, the City mailed out pamphlets containing FOG information with water bills. Per our permit, that should be done twice a year. 

The Planning Board approved revised language in the UDO and it is pending City Council approval. The Chapter 17 changes are under the required construction documents, which specify that new construction needs to have a FOG control plan in accordance with Chapter 70 of the Code of Ordinances. Any discussion of FOG in the UDO references the Code of Ordinances, so that all the information is in one place and there are not pieces in both the UDO and Code of Ordinances. 

Mr. Todd explained that one of the changes will be to better organize the ordinances. Under Chapter 70: Utilities of the Code of Ordinances, the order of articles is (1) General, (IL) Water System, (III) Sewer System, (IV) Water Shortage Response Plan, and (V) Sewer Use Ordinance. They will be reordering the sections so that both water and both sewer sections are sequential. The rest of the changes to the Code of Ordinances are highlighted (Attachment B) and Mr. Todd will walk through them. Staff will be asking the Committee to recommend the changes to the full Council for approval. Mr. Todd also commended the work of Mr. Winans, who put in a lot of time and effort in making the changes to the ordinances. 

Mr. Todd said the first change is switching the Water Shortage Response Plan from Article IV to Article III, as explained above. Next, sections 70-91 and 70-92 were changed to reference sections 70-141(A) and (B), as there are additional definitions in that section and it is simpler to have the information in one place. 

Mr. Todd said section 70-105: Acceptance of wastewater from private or corporate wastewater companies, was cleaned up and references to digested sludge and FOG were included. He added that the changes have more to do with accepting septage. Mr. Winans explained that when they installed two receival stations, one for septage and one for digested sludge, the code did not define the difference between them even though our fee schedule references two different locations. The code was never updated and since it is already being revised, those changes were made. 

Minutes — Council Public Works and Utilities Committee Meeting — July 1, 2026 Page 10 of 14 


{11}------------------------------------------------
The bulk of the changes are in section 70-141 and Mr. Todd stated that they looked at other municipalities’ FOG programs and ordinances to see what was in place. While much of the content was borrowed from other cities and counties, Mr. Winans said itis all built off of federal standards and state administrative code. Mr. Todd said much of this section involves defining the pollutants and different ways of looking at what is prohibited. The first change is under section I(2), as it applies to interceptors and grease traps as pretreatment measures. 

Mr. Daniel asked about the Code’s references to “the director” and asked who that is. Mr. Winans said it would be the director of public works and there are other parts where it could be interchanged with City Manager. Mr. Hooper said he believes it refers to the public works director, but they will clarify. 

Section L details the FOG control policy and contains new language. Mr. Todd said it covers how to prevent FOG and addresses different types of establishments, which can include schools, daycares, restaurants, or any other place that prepares food. He added that it could apply to any establishment that uses oily substances and dumps it down the drain, such as a factory that uses oil in its cooling system. Mr. Winans noted automatic carwashes, as they often have oil/water separators. Section L also addresses regular maintenance and the introduction of emulsifying agents. Mr. Todd stated that he and Mr. Winans talked to the Director of Organic Chemistry at UNC Asheville about Dawn dish soap, as it is an emulsifying agent and technically not allowed under the code. He said they do not want to discourage the use of Dawn, as it is usually a good thing, but when the code references emulsifying agents, it is talking about people who pour Dawn down the drain to unclog their pipes. Using Dawn to unclog pipes is problematic, as it temporarily breaks down FOG and allows it to move through a grease trap, but later coagulates in the City’s wet wells. 

Mr. Todd said section L continues to covera lot of granular details on FOG and section M, where the UDO points to, covers FOG requirements for new construction. This section gives the City a little more control over FOG in new buildings and grease traps will be required for FSEs. It does not tell FSEs what size interceptor to use, but North Carolina Standard Plumbing Code sizing guidelines are provided. 

Section N discusses education and gives introductory information on FOG. Education is the primary means of controlling FOG in a residential setting and while the City will not require residents to install grease traps in their homes, the City is interested in educating residents so they handle FOG responsibly. First, second, and third occurrence actions are listed for residential FOG non-compliance, which includes letters and community meetings. There may be blockages in certain areas if residents pour FOG down the drain because they do not understand the impacts. 

Section N also discusses enforcement for businesses and lists the types of enforcement mechanisms, violations, and violation tiers based on severity and frequency. Tiers will indicate the penalty assessed, which can range from a Notice of Violation to lofty fines with repeated, severe instances of non-compliance. Mr. Todd 

Minutes ~ Council Public Works and Utilities Committee Meeting — July 1, 2026 Page 11 of 14 


{12}------------------------------------------------
said in looking at repeated occurrences, they will use their judgment to determine why another occurrence happened. For example, they will need to determine if someone ignored the City’s warnings, tried something and it didn’t work, or they had an interceptor but did not have it cleaned frequently enough. If they did not ignore the City, it is unlikely that they will be fined for a first or second offense. 

Mr. Todd explained program roll out and communication. During the budget preparation, Mr. Winans was able to repurpose an existing position to create a FOG Coordinator position. The FOG Coordinator will work with the Wastewater Collections ORC to find out where the worst blockages are happening and where to focus their efforts. They also plan to administer a customer questionnaire to assess current compliance. It will include questions about the type of business, how FOG is currently handled, if they have an interceptor, and how often it is cleaned. A questionnaire also serves as a heads up that inspections will be coming in the future. 

Mr. Todd said they would like to start inspections in problem areas within the next 6 months, but the program rollout will be a soft rollout. Enforcement would not start until about a year out, so that businesses have time to clean their grease traps, obtain a grease trap, and get a Notice of Violation before they get hit with a fine. The City wants to work with customers to either provide education on FOG or direct them to resources that can assist them with compliance. Nurturing the relationship with the County Health Department and Inspections Department will also be critical, as they will be the first ones aware of what new restaurants are doing and who will need to install interceptors. Before opening, a new business will have to show they are meeting North Carolina Building Code, which will include the installation of an interceptor, but the City will want to ensure they are sizing their interceptor per the City’s standards, as opposed to the bare minimum that the code requires. Mr. Todd said they want to developa list of resources related to grease trap installation, maintenance, and repair that can also be provided by the County departments, 

Mr. Carson asked if this would be a business opportunity in this area for someone to pick up the grease. Mr. Todd said it would be a good opportunity in the first few years because businesses that want to comply will be seeking that service. 

Mr. Todd listed possible outcomes of the program’s implementation, including a reduction in sanitary sewer overflows caused by blockages, reduction of BOD and TSS at the WWTP, reduction of odor from FOG, labor cost savings due to fewer blockages, fewer health department violations, cleaner restaurants, and costs to business owners for cleaning, maintaining, and/or installing interceptors. 

Mr. Daniel asked who will impose the penalties on businesses and if it will be the FOG Coordinator. Mr. Winans said he would not expect the FOG Coordinator to assess fines and that it will be sent in a letter via Certified Mail by either the City Manager or designee. Mr. Daniel said he would like that to be clear. Mr. Hooper said when this is brought to Council, they will clarify the roles of specific Staff members. 

Minutes — Council Public Works and Utilities Committee Meeting — July 1, 2026 Page 12 of 14 


{13}------------------------------------------------
The City’s FOG Coordinator has been shadowing Henderson County’s FOG Coordinator to see how they do their inspections and what they look for. Mr. Todd said Mr. Winans coordinated that and it has been good hands-on experience to see how they run their program. 

Mr. Carson asked if there has been any thought as to how to defray costs for businesses, such as a grant program. Mr. Winans said he has looked, but he has not found any grant programs that provide businesses with funding to do what they should already be doing with regard to FOG. Mr. Todd said in discussing their list of resources, Mr. Hooper asked if we could find local plumbers who are familiar with interceptors and compile a list of local companies who can help. 

The next steps are to obtain the Committee’s recommendation to the full Council to adopt the proposed changes to the Code of Ordinances, ask the full Council to adopt the proposed changes to the UDO and Code of Ordinances, and implement the “enforceable FOG program.” Mr. Todd said there may be things included in the program that we think will work but we may have to tweak certain pieces after a few months because they worked in another City but did not work here. Mr. Carson asked if DEQ allows for that type of correction process. Mr. Todd said yes. 

Mr. Hooper added that as part of outreach, he would like to reach out to contractors and tradespeople to let them know the City’s requirements are a little different than the State code so that when they are shopping on behalf of customers, they are buying properly sized grease traps. This will help prevent fines being issued to customers who have a grease trap that was not properly sized by a contractor. 

Mr. Carson asked with regard to tiers 4-7, if there is a way to positively identify the contributor that is the cause of blockages. Mr. Winans said yes, in multiple different ways. Public works has a camera that, if they keep seeing blockages in the same area, they can work their way upstream with the camera to see where the blockages are coming from. Mr. Todd added that the FOG Coordinator will also be going into the businesses to see what they are doing and will be able to tell which customers are complying. Mr. Winans said businesses are required to have their records for 3 years, which will include every time the grease trap has been serviced. 

Mr. Wise said there is a lot of information he would like to read through and he is hesitant to approve all the changes without review. Mr. Daniel said he would agree based on the questions they have had after a brief glance at the material. The Committee agreed to individually send feedback to Staff, and it will be brought for discussion at the next Committee meeting. The Committee also approved of Staff sending the draft policy to NCDEQ for review and feedback. 

## Committee Comments 

Mr. Carson said with regard to Public Works performing 36 acres of mowing, if the City wants to reduce mowing, it could do so by planting wildflowers and reducing 

Minutes — Council Public Works and Utilities Committee Meeting — July 1, 2026 Page 13 of 14 


{14}------------------------------------------------
the amount of grass to maintain. Mr. Todd said the majority of the mowing is related to the baseball fields and the requirement by the State to mow the old landfill. Mr. Hooper said he has a few spots in mind that he wants to ask Public Works about, as it may reduce the area bya little. 

## G. Public Comment 

Harvey Sankey said Mr. Todd gave a great presentation and asked if the information is available on the City’s website. Mr. Hooper said the City does not have a public report on FOG, but the information will be in the minutes. 

Mr. Sankey asked what prompted the FOG code changes, to which Staff explained that when renewing its collections permit, NCDEQ said the City needed an enforceable FOG program, otherwise the permit renewal would be harder in the future. Mr. Sankey asked if this program should have been in place a while ago. Mr. Hooper said thankfully our system was enough to meet minimum compliance and NCDEQ did not pull our permit. They also let us know far enough in advance to allow the City to improve its program before its next permit review. Mr. Sankey asked how many non-residential businesses will need to be inspected. Mr. Winans said over 100. Mr. Sankey asked if businesses will be required to sign a document saying they understand what they have to do, to which Staff said no. 

## H. Set Next Meeting - August 5, 2026 at 3:30pm 

The next regular meeting of the committee will be on August 5, 2026 at 3:30pm. 

## I. Adjourn 

There being no further business, the meeting was adjourned at 4:59 p.m. 

## Minutes Approved: August 5, 2026