# MINUTES City Council Public Works & Utilities Committee 

## Wednesday, March 4, 2026 - 3:30 p.m. City Council Chambers 

Members Present: Lauren Wise, Chair, Council Member Gary Daniel, Vice Chair, Council Member Owen Carson, Citizen Member Mayor Maureen Copelof, Ex-Officio 

Staff Present: Wilson Hooper, City Manager David Todd, Assistant City Manager Wesley Shook, Public Works Director Dennis Richardson, Water Treatment Plant Supervisor Aaron Winans, Wastewater Treatment Plant Superintendent Shawnee Cummings, Assistant to the City Manager 

**==> picture [324 x 43] intentionally omitted <==**

**----- Start of picture text -----**<br>
Guests: Mary Roderick (via Zoom), Harvey Sankey<br>Media: David Bradley<br>**----- End of picture text -----**<br>


## A. Welcome and Call to Order 

Committee Chair Lauren Wise called the meeting to order at 3:30 p.m. 

## B. Certification of Quorum 

Assistant to the City Manager Shawnee Cummings certified that a quorum was present. 

## C. Approval of Agenda 

Mr. Daniel moved, seconded by Mr. Carson to approve the agenda as presented. The motion carried unanimously. 

## D. Approval of Minutes - February 4, 2026 Meeting 

Mr. Carson moved, seconded by Mr. Daniel to approve the minutes of the February 4, 2026 meeting as presented. The motion carried unanimously. 

## E. Norton Creek Restoration Phase 2 and 3 

Mr. Ray explained that a few years ago, the City received a grant and successfully restored a portion of Norton Creek along Silversteen Park. There was a bend in the 


{2}------------------------------------------------
stream that would have caused damage to the restored section, so the City obtained additional grant funding and finished restoration of that section last week. 

The City pursued a planning grant for the design of streambank restoration from Cashiers Valley Road to Rosman Highway. The City received the grant and completed the 30% design work for that section, which incorporates a brownfield and Tannery South. A public engagement session was held at the Mary C. Jenkins Community Center, but there was low turnout, so one or two additional public engagement sessions will be held. 

Mary Roderick with Land of Sky presented slides on the project that will cover 3,320 linear feet of stream (Attachment A). The presentation covered existing streambank conditions, proposed design, goals of the restoration, project cost estimates, reintroduction of Brook Trout, and the status of conservation easements. There have been8 letters of intent signed for conservation easements and 3 funding applications have been completed. If awarded, the funding will be used to take design to 100% and for construction. Mr. Ray noted that a deadline for one of the grant applications came up very quickly, so Staff did not have time to take it to Council for approval before applying. Therefore, if awarded, it will be brought to Council before the grant is accepted. 

Mr. Wise asked if the Hillview Culvert repair on Cashiers Valley Road will impact the project or timeline for the streambank restoration. Mr. Todd stated that it should not have any impact, as the Hillview Culvert repair should be completed this summer and the streambank restoration will likely start in about a year. 

Mr. Wise also inquired about the comments received at the community engagement session. Mr. Ray and Mayor Copelof both stated that the response was largely positive, some property owners even filled out their consent forms at the engagement session, and some expressed willingness to talk to their neighbors. Mayor Copelof said the only problem was that the notice letters were sent out a little late, so the turnout was not as big as they had hoped. The next engagement session will also have a virtual option. 

Mr. Carson added that one big change, especially with a restrictive conservation easement, is that property owners will not be able to manage their land the way they used to. It is a significant change in land use and the City will need to communicate the changes to landowners unfamiliar with the process. Mr. Carson also stated that landowners who do not participate will likely lose land due to erosion so it is important to communicate that and obtain as much participation as possible. 

## F. Project Updates - Mr. Todd presented the following updates: 

1. Public Works Update 

Mr. Todd compiled a list of updates on work performed by Public Works employees in the past 30 days, outside of their normal scope of work and day-to-day responsibilities. 

Minutes — Council Public Works and Utilities Committee Meeting - March 4, 2026 Page 2 of 10 


{3}------------------------------------------------
## Water 

Eagle Point Pump Station — cleaning, repairing, painting, new flooring Performed: 3 leak repairs, 4 leak searches, 5 hydrant repairs/replacements, 1 valve box replacement, 2 pressure tests, flushed one water main, located 2 water lines, located one meter box, installed 3 backflow preventers, installed one new tap. Assists: Sanitation & Streets Assists -6, NCDOT - 1 

## Sewer 

Cleaned 11,091 feet of sewer mains, required to clean 10% per year Video inspected 3,166 feet of sewer 

Check and/or repaired 6 sewer blockages Sewer Line Repairs: 6 Locates: 68 (water and sewer lines for 811}; located 1 water tap Dye test and sewer inspections: 2 Inflow Repairs: 2 

Assists: Sanitation —- 1, Water — 6 (main breaks, water line replacements, etc.), Streets - 1 (sidewalk & street repairs) 

## Sanitation 

Collected: Garbage — 262.90 tons 

Recycling — 67.66 tons 

Cardboard - 17.43 tons 

Special Pickups & bagged yard debris (Paid) -27 loads 30 small dump truckloads of brush 20 large dump truckloads of brush 

## Streets 

Recycle Cart Delivery/Pick Ups - 10 Sign Repair/Replacement- 18 Sidewalk Repair - 21 Patch utility cut -14 Installed 4 truncated domes Installed 2 storm drains Repaired Potholes — 4 Assists: Water — 2, water leaks 

## Garage 

Completed 255 fleet maintenance work orders. 

## Building & Grounds 

Installed 8 new LED lights at water plant Bike path clean up at Railroad Depot and Sports Complex Installed split rail fence on Greenvitle Hwy at school Cleaned up trees/storm debris at Hap Simpson 

Cleaned up old wiring on Ground Floor of City Hall that's notin use Covered broken windows in the “old apartment” in Co-Ed movie theater Fixed broken light at Clemson Plaza 

Installed new breaker at Public Works for car lift Installed new shelving for the PD in Evidence Room Cut trees on Tannery North for the bike path prior to Bat Moratorium Installed new doorknob and lock on entry door at City Hall Spread fertilizer on all city owned flower beds Completed all routine work orders and 10 non-routine work orders Daily baseball field maintenance 

Minutes — Council Public Works and Utilities Committee Meeting — March 4, 2026 Page 3 of 10 


{4}------------------------------------------------
## 2. Stormwater Master Plan 

McAdams is contracted for the Citywide Stormwater Master Plan and is currently advancing Phase1 of the project, mainly focusing on Existing Conditions Analysis. This effort is supported by desktop analysis, geodatabase development and management, analysis of existing stormwater systems, and preliminary CIP prioritization planning, and UDO updates. 

CCTV services began on February 16, 2026 and will conclude in early April. CCTV field crews will work from March 30th to April 8th to complete their collection. McAdams held a UDO Workshop with City of Brevard staff and will revisit discussions with staff on March 31, 2026 to finalize UDO recommendations. Hydraulic modeling is ongoing and will be finalized in June. 

Below is the overall schedule: 

1. Overall Project Schedule and Scope: a. Phase 1 completed in fiscal year 2026 (June 2025 - June 2026) i. Identification of Projects and Capital Improvement Planning 1. March: Stormwater UDO discussion held on 2/17 a. Next scheduled meeting on 03/31 to discuss action items. 

2. March - April: CCTV crews mobilized the week of 02/16 a. CCTV crew will complete work on week of 03/30 +04/06 

3. March - April: Finalizing existing conditions models + Prioritization 

4. April: Final field visits for any missing data 5. April - June: Report writing + finalizing deliverables 6. July: Submittal to City of Brevard for review and approval 

b. Phase 2 completed in fiscal year 2027 (July 2026 - June 2027) i. Schematic Design and Identification of Funding 

## 3. Hillview Street Culvert 

Project is out for bidding. There are currently 12 plan holders. Ten are contractors and two are plan houses. One contractor has indicated that he will not bid and a second has indicated it is unlikely. Both cited an excess backlog of work as the reason for their response. Bids are due on Tuesday, March 24th at 2pm. 

Minutes — Council Public Works and Utilities Committee Meeting — March 4, 2026 Page 4 of 10 


{5}------------------------------------------------
**==> picture [202 x 14] intentionally omitted <==**

**----- Start of picture text -----**<br>
Hillview St. Culvert rricstar<br>**----- End of picture text -----**<br>


**==> picture [441 x 176] intentionally omitted <==**

**----- Start of picture text -----**<br>
City of Brevard, NC Display week:<br>et oe DE BETOS OT<br>kd Prooess eran ew t/t Xe Se Se ir SSeS a SS EI<br>—fevestigation<br>Tow wes WOES fi<br>Fina? Design Phase:<br>Tots WANS wi2r26<br>Permitting Services<br>Tots! wanes araaee8 ee eeee<br>mowetorigtiog<br>(ema<br>va reo tela AIT Y end<br>**----- End of picture text -----**<br>


## 4. Water Treatment Plant Renovation 

## Work to date: 

1. New Clearwell was set to be disinfected week of 3/3/2026. There was a slight seepage in the tank, so CMT (concrete) has been contacted to meet onsite. The seepage was near the draw/fill line. Once this is resolved, disinfection will proceed. 

2. Media removed from the filter bay #1 - and replacement media begins 3/3/2026 3. Ofthe 20 new actuators planned to be installed, only 4 remain. Carolina Specialties are working with Brevard water plant staff to finalize and calibrate opening/shutting of each actuator based on back pressures. 

4. New generator arrived and has been placed on its new pad behind the pump building. 

## Upcoming work: Work over the next couple of months 

1. Complete Clearwell work on seepage point. 2. Disinfect the tank. 3. Weare awaiting the delivery date of the new pumps and controls. 

**==> picture [437 x 127] intentionally omitted <==**

**----- Start of picture text -----**<br>
City of Brevard - Water Treatment Plant Improvements:<br>NCDEQ SRP-D-ARP-0222<br>BrownPA - 20042<br>—————————— ae<br>IProjectAdverise Ppp yy Tt eee<br>lBidMarch25,2026 pte Pet<br>fRE-BidApritas.2025 dT<br>Ja720/2025-NCDEQBID dT<br>|May30,2025May29,NCDEQATAlenerreceved20225 Notice ofAwardreceived packageforApproval Ss|| ss] S| «S[ | | | || Om|TTTTTTOT TT TTTT<br>Constructiona6sDaysljune10,2025ExecuteContract-NoticectoProceedCT|| CT| [| | Mm TT |ttt| tT tT [tT]<br>**----- End of picture text -----**<br>


Minutes — Council Public Works and Utilities Committee Meeting — March 4, 2026 Page 5 of 10 


{6}------------------------------------------------
## 5. Water and Sewer Asset Inventory Assessment 

a. Water System Asset Inventory & Assessment 

Field Work to Date: 

e Completed with the exception of the missing items to be located by City Staff. 

## Current Status: 

- e Model has been constructed and items identified. e Awaiting PRV information from the City. 

- e Flow tests have been completed. e System partially calibrated. 

- e Awaiting future demand (upcoming development) information. 

- e Completed recommended improvements based on failing infrastructure. 

- e On-site inspection and assessment of the existing pump stations completed. e Demand projections based on information provided by Planning Department completed. 

- e Preparation of a proposed improvements program based on future demand. 

## Next Steps: 

- e Finalize Report. 

- e Revisit Financial Impact due to CIP changes. 

## Schedule of Remaining Tasks: 

**==> picture [379 x 201] intentionally omitted <==**

**----- Start of picture text -----**<br>
||||||
|---|---|---|---|---|
|Task|Completion Date|
|Field Work|(not including missing items)|completed|
|Initial Model|(for calibration)|completed|
|Flow Tests|(by City of Brevard)|completed|
|Analysis of Ex. Water System|completed|
|Update Demand Projections with regard to TAZ data|completed|
|Demand Projections based on upcoming development|completed|
|Capital|Improvements|Program|completed|
|Financial|Impact|Being|revised|
|Project Close|out|March|6,|2026|

**----- End of picture text -----**<br>


## b. Sewer System Asset Inventory & Assessment 

Current Status: 

e Fieldwork is 100% complete. 

Minutes — Council Public Works and Utilities Committee Meeting — March 4, 2026 Page 6 of 10 


{7}------------------------------------------------
- e Sewer mapping is 100% complete. e Preparing an infrastructure replacement program. e Demand projections based on NCDOT TAZ. 

- ¢ Demand projections based on information provided by Planning Department completed. 

- e Report has been completed. e CIP and Financial Impact have been completed. 

## Next Steps: 

- e Schedule presentation to City of Brevard 

## Schedule of Remaining Tasks: 

**==> picture [420 x 232] intentionally omitted <==**

**----- Start of picture text -----**<br>
Task Completion Date<br>, . . rr ‘Completed - additional<br>Field Work (not including missing items) manhole being located<br>Smoke Testing of Kings Creek Basin completed<br>Identify and Rate Critical Infrastructure TBD<br>Update Demand Projections completed<br>Identify Areas Needing Sewer with Planning Dept. completed<br>Update Existing Infrastructure Assessment completed<br>Capital Improvements Program - Failing Infrastructure completed<br>Capital Improvements Program —- Future Development completed<br>Financial Impact completed<br>Present to City of Brevard TBD<br>Project Close-out Completed<br>**----- End of picture text -----**<br>


6. Gallimore Sewer Rehab Update 

## Gallimore Basin Sewer Rehab Change Order #2 

- e The pipe lining along County Club Road and Caldwell Street is complete. e The manholes along Country Club Road and Caldwell Street are complete. e BLD has lined the service laterals along Caldwell and Country Club Rd. e The Contractor is currently negotiating with a Sub to perform point repairs along England St and install cleanouts. 

- e Contractor is overdue in providing an updated schedule. « England Street Gravity Sewer has been lined e 3 sewer services along Caldwell St remain to be lined after point repairs. e 3services along England Street to be lined. e 10cleanouts to be installed. 

Minutes — Council Public Works and Utilities Committee Meeting — March 4, 2026 Page 7 of 10 


{8}------------------------------------------------
- e Contractor waiting on Sub to schedule excavation and repair of existing services and installation of cleanouts. 

**==> picture [454 x 124] intentionally omitted <==**

**----- Start of picture text -----**<br>
—_ === enonenom Ur SUOMI! ——-=<br>ul a —_ — .<br>Iypme | SS a<br>i!oe re a ee (ne<br>Eeeeeeee<br>LOA LGL LAO GL LAD OL GL LIP DEEOLO ELS LLOOIAALAESELIEILILIA L AS<br>**----- End of picture text -----**<br>


## 7. Sewer Lift Station Rehabilitation Project 

The Pump Station Rehab and Replacement project Contract has been executed, and a preconstruction meeting was held on 6/30/25. 

TP Howard is currently mobilized at the Gallimore Pump Station and construction continues. 

- e The contractor has installed the pump station wet well. 

- e The contractor has begun to install the grinder vault. Vault was to be installed Friday, February 27th. 

- e The Contractor has begun removal of excess dirt. 

- e The meter vault and valve vault have been delivered to the jobsite. 

Shop drawings and submittals are continuing to be reviewed. 

## Change Order No. 1 (Grinder Vault) 

- e The Change Order is complete, and Contractor has been sent final the Change Order. 

- e Associated grinder vault shop drawings have been approved and the grinder vault was delivered to the jobsite. 

Progress has been made on both the Fish Camp and Gallimore Road easements. Terms have been reached and staff are currently finalizing paperwork. 

**==> picture [441 x 125] intentionally omitted <==**

**----- Start of picture text -----**<br>
||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|Sewer Pump Station Rehab|Project|
|aTask|Hut_|aug |SepeeOct||Nov|Dec|Jan [Feb |Mar|Apr|[May|Junee[Jut_|Aug|Sep| Oct|[Nov|Dec|Jan|[Feb||Mar||
|cauimorerumpstationcizisies7ismey||_||||||Pt|tT|tT|
|FishcampPumpstaionssiraze-sisue||_||||||||||||||||||||Lt|
|wisonPumpstauonPurchourecteampsnaressvorssize-siaoy|||_||||||||||||||||||||||||||||ft}||[Tt]|||P|t|t{||
|anparundingdeactne(decemeerst.2026||||||||||||||||||||||||||||||||||iw|||||||
|corn-finatcompietondareizen||_||||||||||||||||||||||||||||TdT dt|dT|r||I|

**----- End of picture text -----**<br>


Minutes — Council Public Works and Utilities Committee Meeting — March 4, 2026 Page 8 of 10 


{9}------------------------------------------------
## 8. WWTP Renovation and Upgrade Project 

In February, The City received the Letter of Intent to Fund for the Phase 1 Helene funding and was approved by Council. City staff, with assistance from KCI, has also submitted a request to DWI to designate the remainder of the City’s appropriations funding to the construction of Phase 1. 

Over the coming weeks, KCI will be finalizing their internal review of the permit level Phase 1 design drawings and Phase 2 & 3 PER. KCI is anticipating sharing these documents with the City and reviewing these documents in person with City staff in March. During this meeting, KCI will discuss potential funding options for the design of Phase 2. 

Following this meeting, KCI will make any necessary changes requested and begin the permitting and funding approval process for the Phase 1 design. 

**==> picture [472 x 262] intentionally omitted <==**

**----- Start of picture text -----**<br>
BREVARD WWTP PER/PHASE 1 & 2 UPGRADE DESIGN - ESTWAATED PROJECT SCHEDULE fe Ké 1 ir ISL OCF<br>ese] nmr Jn oe i fd m= se ei J n= Too Fon fe oes roscoe Fern bcd<br>uf | —" rnomaammonee fe St Ss oea omeoe [oe] an a a es a ee oe aes +++} —4—-+ + 4 ¢ 4 ff 4 4g<br>a es | eofir‘| ij Fass SEEEEEEEESee 222s222= oe ieSErerre Ts HS Bd ts et SS  SHEETes BY Et an nan =I mal mi 5 C t =<br>a eeeee ee<br>GREVARD WWTP PERIPHASE 1 & 2 UPGRADE DESIGN - ESTIMATED PROJECT SCHEDULE me KCI Tecunotocies<br>a<br>rene] __—_—oescrwrion | reten_| Jan | | ar | A | or an | ut || See | et |r| One| an |e | ter | || | nt |e |<br>proposed Sede CSCS = aS a a<br>Praca<br>ee eT i<br>[——Permmeg io] = Ss aael a ee a =a SS =<br>Ss |. H e auorks ana Agin PrivaSz= fa =-TEEEEEEEETEEETE= = ae B Ie<br>fs ee me tee pe tt<br>si11 | PresiminaryDesign (Start OweTBO ttt = =o =e<br>“ — Basing& Conan a VV!<br>seit Pears Unpase 15} a a se os ee a es Se ce ee Oe<br>a ttttt ttt t.tst<br>**----- End of picture text -----**<br>


## 9. Public Comment 

Harvey Sankey asked about Land of Sky and its work with the City, to which Mr. Todd explained their role as a regional council, how they assist the City with projects and grant applications, and how the City sometimes contracts their services. Mayor Copelof added that she is also the Chair of the Land of Sky Board of Delegates and that the services Land of Sky provides are intended to augment the work of cities and counties. 

Mr. Sankey also asked if the request for additional personnel in the Public Works department will come to the Committee first. Mayor Copelof said that those requests do 

Minutes — Council Public Works and Utilities Committee Meeting — March 4, 2026 Page 9 of 10 


{10}------------------------------------------------
not come to the Committees. Mr. Wise added that the reason that each Committee has 2 Councilmembers is so that a few Councilmembers know what is going on in each group. 

Mr. Carson stated that he may need to recuse himself from some oversight of the Committee, as he is a subcontractor for a contractor selected for an interview for work on the Estatoe Trail. He explained that he may be the best representative to attend, and he does not want it to conflict with the role of the Committee. Mr. Todd stated that this Committee will not be involved in the selection process and that he does not see any conflict with Mr. Carson's role'on the Committee. 

## 10. Set Next Meeting - April 1, 2026 at 3:30pm 

The next regular meeting of the committee will be on April 1, 2026 at 3:30pm. 

11. Adjourn 

There being no further business, the meeting was adjourned at 5:13 p.m. 