Report
He reviewed with Council why the $150 Million GO Bond package is the recommended amount (1) Meaningful, but achievable (a) Longer timeline to execute, but double 2016; and (b) Better prepared, lessons learned from 2016; (2) Reasonable taxpayer burden; and (3) Maintains safe amount of debt per capita.
City Council Meeting (Apr 9, 2024) · April 9, 2024 at 12:00 PM
What was said
And then finally, the recommended amount, we're suggesting 150 million over two votes. And why did we land on this amount? Well, one thing, we think it is a meaningful amount, and so it will allow us to address some of our capital needs. Obviously not all of them. It provides us with a longer timeline to execute, and especially since this is double the amount that we issued in 2016. reasonable taxpayer burden so it lessens the cost overall and it allows us to maintain a debt per