The City of Asheville’s Infrastructure Recovery Board held a special virtual meeting on November 10, 2025. The session focused on establishing the board’s operational framework, including the adoption of rules and the election of officers, as well as providing a comprehensive update on the city’s infrastructure recovery efforts and funding sources.
Key Decisions
The board took four formal actions during the meeting, all of which passed by a vote of 10-0. First, the board approved the minutes from the previous meeting held on November 4, 2025. Second, the board adopted the official Rules of Procedure, which outline how the board will conduct meetings, manage quorum, and handle public participation. Third, the board elected Charlie Huguenard as Vice-Chair. Finally, the board elected Tim Ormond as Chair.
Discussion Highlights
A significant portion of the meeting was dedicated to an informational presentation on the progress of recovery projects and available funding. Staff presented an overview of the damage inventory, which includes 135 damaged items across various city departments such as Parks, Public Works, Water Resources, and Facilities. The presentation detailed the city’s navigation of three primary federal funding sources: FEMA Public Assistance (PA) for repairing storm-damaged infrastructure, the Hazard Mitigation Grant Program (HMGP) for reducing future risk, and the HUD Community Development Block Grant-Disaster Recovery (CDBG-DR) for long-term recovery and economic revitalization.
Specific project updates were shared, including the design phase for the Bee Tree Dam, efforts regarding temporary pretreatment facilities, and debris removal operations. Staff also discussed a "design it twice" approach for larger projects, where the city develops two design options: one for basic repair to secure PA reimbursement and another incorporating improvements to leverage other funding sources. Additionally, the board discussed upcoming public engagement opportunities, including a December 10 open house for the Azalea Park and French Broad River projects. Board members emphasized the importance of engaging with their networks and attending community meetings to gather feedback.
Follow-ups
Staff members explicitly agreed to several follow-up actions during the meeting. D. Tyrell McGirt, the Parks and Recreation Director, along with Christy Bass, the Resource Management Division Manager, and Tim Ormond, agreed to schedule a meeting to plan the agenda for the next board meeting. Additionally, D. Tyrell McGirt and Christy Bass agreed to provide board members with a final project description for water resources projects. Board members were also encouraged to engage with their networks in preparation for upcoming public engagement events.
Impact
This meeting marked a foundational step for the Infrastructure Recovery Board, formally establishing its leadership and procedural guidelines to ensure transparent and consistent decision-making. By adopting the Rules of Procedure and electing officers, the board is now structured to effectively advise the City Council on rebuilding infrastructure with a focus on long-term resilience. The detailed review of federal funding mechanisms and project statuses provides residents with insight into how the city is utilizing resources to repair damage and mitigate future risks from natural hazards.