Planning and Zoning Commission
October 7, 2026 at 5:00 PMIn person70 Court Plaza, Asheville, NC 28801, USA - First Floor Conference Room
- 3 h 33 minlength
Event Recap
Sunshine AI summary of the meeting video and documents. How we make these pages
Meeting Overview
The City of Asheville Planning and Zoning Commission held its regular in-person meeting on October 7, 2026. The agenda included the approval of previous minutes, updates on legislative and administrative actions, two public hearings regarding conditional zoning requests, and a discussion on the Commission’s annual report.
Key Decisions
The Commission recorded three votes, all of which passed with a 6-0 tally. First, the body approved the action minutes from the September 2, 2026 meeting. Second, the Commission voted to approve the conditional rezoning request for the Costco project located at 264 Enka Heritage Parkway, 274 Enka Heritage Parkway, and 1455 Sand Hill Road. This approval included a recommendation to revise the condition concerning tree canopy preservation to eliminate explanatory reasoning, leaving only the technical requirement. Third, the Commission voted to approve the amendment to the conditional zoning at 21 London Road. This approval included conditions to retroactively eliminate a prior condition from the May 2024 ordinance, require publicly available bike parking, and recommend that the applicant work with city staff to explore resilience measures.
Discussion Highlights
Staff provided updates on several ongoing initiatives, including a recent discussion at the Housing and Community Development committee regarding the potential elimination or consolidation of the RS2 zoning district. Staff noted that RS2 areas are largely environmentally encumbered or already occupied, and the Commission agreed to place a formal discussion on this topic on the November agenda. Additionally, staff announced that City Council has authorized a contract with Opticos Design Inc. to lead the Comprehensive Plan update and Unified Development Ordinance (UDO) rewrite, a project estimated to take two and a half years. Staff urged the Commission to continue pursuing incremental updates rather than pausing all work for the duration of the project.
During the public hearing for the Costco project, the applicant proposed a 168,258 sq. ft. retail building with technical modifications to parking and tree canopy preservation. Staff recommended approval, noting the project’s compatibility with future land use and infrastructure. In the hearing for 21 London Road, commissioners raised significant concerns regarding flood resilience following Hurricane Helene, noting the building is partially within the 100-year floodplain. Commissioner Anna Zuevskaya stated, "We are talking about flooding, and we are talking about public safety... We have communities right around Asheville... that have moved to a four foot plus base for elevation in their ordinance. And we are lagging a little behind." Commissioner Brenton Faircloth emphasized the need to prioritize anti-displacement efforts, stating, "I feel as though the anti-displacement needs to be a top one... I feel uncomfortable going much further without seeing like legitimate progress gained there."
Community Input
During the public comment period for the Costco project, a representative of the National Neighborhoods Coalition raised concerns about the tree canopy calculation. The commenter argued that the calculation should apply to the full site rather than just the disturbed area and recommended that the applicant work with the Urban Forester to meet the 15% standard. No public comment was received for the 21 London Road hearing.
Follow-ups
Staff agreed to place a formal discussion on the RS2 zoning district on the November agenda, including providing GIS data and procedural details. Staff also agreed to share the scope summary of the Comprehensive Plan update in advance of the next meeting. Additionally, staff agreed to bring a representative from the Asheville Development Authority or Housing Authority to a future meeting to discuss affordable housing initiatives and data.
Impact
The decisions made at this meeting advance two significant development projects in the city. The Costco project, which includes a historic clock tower and a greenway path, will proceed to City Council for final approval. The 21 London Road project, which increases residential units and building height, will also go to City Council, with added conditions focused on flood resilience and bike parking. The Commission’s focus on flood protection and anti-displacement in the annual report discussion highlights the body's intent to address critical community needs in upcoming zoning and planning work.
Meeting Video & Transcript