Town Council Regular Meeting Aug 24 2026
August 24, 2026 at 5:58 PM
- 1 h 50 minlength
Event Recap
Sunshine AI summary of the meeting video and documents. How we make these pages
Key Decisions
The Town Council approved the agenda for the August 24, 2026, regular meeting by a 7-0 vote. The council then voted 7-0 to approve the consent agenda, which included items A through N. These items comprised the minutes from previous meetings, the FY2025-2026 tax settlement, the appointment of Morgan Worley as Tax Collector, the order of collection for FY2026-2027 property taxes, the monthly tax report, FY2026-2027 budget reappropriations, a road closure ordinance for the Weaverville Business Association (WBA) Art in Autumn event, board appointments for the Board of Adjustment and Planning Board, change orders for the Water Resiliency Project, a zoning map amendment for 21 Parker Cove Road, code amendments for parking, a memorandum of agreement for grant services, and a volunteer opportunity with the LOSRC Area Agency on Aging.
Separately, Council Member Andrew Nagle moved to approve the Amendment to the US Cellular Tower Lease Agreement, which passed by a 7-0 vote. The amendment extends the lease term to December 31, 2046, with options for renewal, and sets the rent at $1,800 per month for the first five years beginning January 1, 2027.
Discussion Highlights
During the consent agenda review, staff explained that the Water Resiliency Project change orders add $3,288 and 10 days, and $11,451 and 13 days, respectively, bringing the total project cost to $1,842,487 with a completion date of October 4, 2026. Staff also noted that permits for the water treatment plant expansion were submitted or would be submitted early in the week following the receipt of final items from the consulting engineer. Regarding the grant services memorandum, staff clarified that the town is not obligated to pay the up to $30,000 in disaster recovery funds; the funds come from the North Carolina League of Municipalities’ allocation. Council Member Young asked for clarification that the $30,000 is not an obligation from the town’s budget and inquired about the town's competitiveness for the service.
The council received a presentation from Captain Sherrie Stokes and a member of the public of the Salvation Army regarding their mission and programming in Buncombe County. They discussed the 80-bed Center of Hope shelter, which will pause services from November to April 30 due to the loss of ARPA funding, and the CORPS Community Center at 750 Haywood Road, which reported a 300% increase in food pantry distribution. Council members asked questions regarding volunteer support for the Christmas Kettles campaign and the IRS filing structure of the organization.
Council Member Young reported on the AdventHealth public hearing for a 92-bed certificate of need, noting that approximately 200 attendees were present, with two-thirds supporting AdventHealth. He detailed the construction timelines, including medical office building steel erection starting mid-September 2026 and hospital steel erection starting December 2026. Council Member Phil Barnett asked why the state must approve hospital bed additions, expressing a belief in fair market competition.
Regarding the Weaverville Watershed Property, Assistant Town Manager Jackson announced a public information meeting for September 10 to discuss a cable-logging salvage harvest to address damage from Hurricane Helene and reduce wildfire risk. Council Member Mark Endries noted that the United States Forest Service will install fire breaks after logging is completed.
Community Input
No members of the public provided comments during the General Public Comments segment of the meeting.
Follow-ups
Assistant Town Manager Jackson stated that a budget amendment for the Weaverville Watershed Property project will be presented for approval in the next couple of months. Additionally, staff will bring equipment financing proposals to the council for approval at the September 28, 2026 meeting.
Impact
The approval of the US Cellular Tower Lease Amendment secures a long-term revenue stream for the town, with rent set at $1,800 per month for the initial five years. The consent agenda approvals, including the appointment of Morgan Worley as Tax Collector and the adoption of the FY2026-2027 order of collection, ensure the continuity of tax administration and budget management. The Water Resiliency Project changes keep the project on track for completion in October 2026, while the grant services agreement provides access to technical assistance for disaster recovery without direct cost to the town’s budget. The discussion of the Weaverville Watershed Property outlines a plan to mitigate wildfire risks and restore access to the property, with a public information meeting scheduled for September 10 to engage the community.