Skip to main content
Consent agenda

Changes and Site Readiness

City Council Meeting Agenda Packet (PDF) · March 3, 2026 at 6:00 PM

If the contract scope is modified after Shotcrete Contractors has delivered materials or commenced work, or if the project site is not ready for Shotcrete Contractors to begin work as scheduled, or if other delays occur that are outside the control of Shotcrete Contractors (including but not limited to coordination issues, third-party delays, or site inaccessibility), the Client agrees to compensate Shotcrete Contractors at a rate of $600.00 per crew-hour for lost time. This charge shall apply to each hour a mobilized crew is unable to perform work due to such circumstances.