Report
City of Lenoir - Projects: Greenway LAPP Project
City Council Budget Retreat Packet (PDF) · March 24, 2026 at 6:00 PM
Funding for Connection Project Segments 1 through 5 in the amount of $2,167,750 with a city cash match of up to $433,550. The project proposes five greenway segments totaling approximately 1.37 miles. Design was completed in 2024; M&C is securing Right Of Way. STIP schedule updated to PE/DESIGN: FFY26, ROW: FFY27, UTILITY: FFY27, CONSTRUCTION: FFY28.