Finance & AdministrationB

Approval; Additional Service Agreement with Maurer Architecture for services related to the Campus Improvements Project. Staff is requesting consideration for two agreements with Maurer Architectures for additional services for the Campus Improvements project. The project includes three (3) distinct components: renovation of the Historic Old Lenoir High School Auditorium, Gymnasium, and new construction of the OVT Farmers’ Market Pavilion at the former LEOS site on West Avenue. The cost of that contract was $325,000. Due to changes identified during construction, it has been necessary to add additional services to the scope of work. The total amount of the two agreements is $22,300, ​as submitted.

Committee of the Whole Meeting · August 25, 2026 at 8:30 AM