Consent agenda
Change Order Log and Prime Contract Change Orders (PCO #003, #004, #006, #008, #010)
City Council Meeting · September 1, 2026 at 6:00 PM
Approval of proposed change orders for the LHS Campus Phase I project with JM Cope, including Gymnasium Chimney Demolition Concealed Conditions ($10,046.48), Electrical Charges ($6,108.91), ADA elevator access and ramp ($8,734.97), Dumpsterpad and Gym Ramp ($7,670.18), and Concession Structural Floor Support ($28,632.00). Total proposed change: $61,192.54.