Multimodal Transportation Commission Meeting Recap: August 24, 2022

The City of Asheville’s Multimodal Transportation Commission convened on August 24, 2022, to review project updates, discuss infrastructure decisions, and receive reports from its subcommittees. The meeting began with the approval of the current agenda and the minutes from the July 27, 2022 meeting, both of which were approved unanimously. The primary substantive discussions centered on the status of the I-26 Connector Project, the Asheville Unpaved natural surface trail initiative, and a significant shift in plans for Biltmore Avenue repaving and bicycle lanes.

A major point of discussion was the decision to phase the installation of bicycle lanes on Biltmore Avenue between Patton and Hilliard. Staff reported that a decision had already been made at the City Manager and staff level to not install bike lanes as part of the current North Carolina Department of Transportation (NCDOT) repaving project. Instead, the city will proceed with loading zone improvements and conduct further public engagement before implementing bike lanes in a future phase. Staff clarified that adding bike lanes during the current NCDOT project would not have required additional city funds, as the road was being restriped regardless, but the decision was made to evaluate the loading zone changes first. This decision drew strong reactions from Commission members. One member stated, "I do think this decision is absolutely wrong... I think that if we’re not going to get this now, we’re going to reevaluate more of this... I’m just letting you know, I’m going to push hard to give access to everybody in our community to transportation back to downtown." Another member expressed disappointment, noting, "I’m really disappointed with the decision... You already have support for this thing. How much more support did you need to have? Merriman just flooded it." No formal vote was taken by the Commission on this item, as it was reported as a staff-level decision.

The Commission also received an update on the I-26 Connector Project from the Director of Transportation, who confirmed that the project remains on schedule despite state budget changes. The Director stated, "I-26 connector project was not affected by that [state budget changes] at least now. So it’s still on its schedule." He noted that the "Record of Decision" is scheduled to be signed at the end of September. Staff confirmed they are working to identify the $44,000 local match needed for a corridor planning study grant and have a meeting scheduled with the budget team to identify this funding, hoping to present a budget amendment to City Council on September 13.

Regarding the Asheville Unpaved initiative, a staff member presented the status of five pilot natural surface trail locations. Staff addressed concerns about trail density and erosion, explaining, "Our concept to put in a new style of trail and a new trail system that would support a lot of hiking, but also some exclusive mountain bike single tracks up there to get the mountain cyclists off the other trails... is our plan." Staff confirmed that neighborhood meetings will continue for the East End, Valley Street, Oakhurst, and Kenilworth neighborhoods to address concerns about trail density and event fatigue. Following these meetings, a citywide public campaign, including a survey and meetings, is planned for late summer or early autumn. Staff noted that construction is unlikely to begin until spring, pending fundraising.

Updates from the Transit, Greenway, and Bike committees were also provided. Staff announced that the next joint Transit/Multimodal meeting will be held on September 20, featuring a tour of the downtown transit center and the parking garage. The French Broad River West Greenway ribbon-cutting ceremony is scheduled for September 15 at 4:30 p.m. Additionally, staff agreed to hold a discussion with the Bike Committee in October regarding comprehensive bike lane maintenance issues, including encroachment, debris, and pavement irregularities. A staff member also agreed to connect with NCDOT regarding traffic and construction concerns on Sweeten Creek Road raised by the Neighborhood Advisory Council liaison.

No public comments were recorded for this meeting. The Chair stated, "We were notified there was no public comment for our meeting today."

The decisions and updates from this meeting have direct implications for local transportation and recreation. The deferral of Biltmore Avenue bike lanes means that while loading zones will be improved in the near term, cyclists will not have dedicated protected lanes in that section until a future phase, which staff indicated is likely to be a budget request for the next fiscal year starting July 1, though it could happen sooner if funding is found earlier. The I-26 Connector remains on track for its Record of Decision in late September, and the Asheville Unpaved trails are moving toward a citywide engagement phase before any construction begins in the spring.