Meeting Overview The City of Asheville Greenway Committee met on May 5, 2022, to review ongoing greenway projects, discuss the Greenway Action Plan (GAP), and address changes to the State Transportation Improvement Program (STIP). The agenda included staff updates on construction and funding, a presentation by the Metropolitan Planning Organization (MPO) regarding regional transportation funding deficits, and a discussion on a proposed greenway etiquette campaign.

Key Decisions The committee approved the meeting minutes and the agenda without objection. No other formal votes or motions were recorded during the session.

Discussion Highlights Staff provided updates on several major projects. The French Broad River West Greenway is on track for completion in late July or early August 2022. For the Swannanoa River Greenway, staff reported a $2.5 million funding shortfall to complete the project in one phase. Staff are applying for Tennessee Valley Authority (TVA) funds, with a decision expected in October, and Surface Transportation Block Grant (STBG) funds available in 2027. If TVA funds are not received, the project may be split into two sections. Other updates included the Nasty Branch Greenway, where design and permitting are underway with construction expected in late 2022 or early 2023, and the North Radford Greenway, where engineering requests were paused to align with new STIP guidelines and Riverside Drive improvements.

A significant portion of the meeting focused on a presentation by Tristan Winkler of the MPO regarding the draft 2024–2033 STIP. Winkler explained that NCDOT is facing an $8 billion funding deficit, leading to the decommitment of over $1.2 billion in regional projects. While most standalone bike and pedestrian projects funded by MPO federal funds were retained, the Swannanoa River Road widening project, which included significant bike and pedestrian components, was decommitted. Winkler noted that the MPO has preliminarily approved $2.5 million in federal funds for the Swannanoa Greenway, which may help cover the city’s budget overrun, though scheduling is not yet finalized. He emphasized that without these changes, there would be no new statewide mobility projects until 2041 and no new regional impact projects until 2053.

Committee members expressed strong concern over the removal of the Swannanoa River Road project from the STIP. One member stated, "I really feel like we have to do this [swap]... It's critical." Another member assessed that the Department of Transportation would prefer not to build the Swannanoa Greenway, while a third member described the current infrastructure as being "one weather event away from total failure." Members discussed the MPO’s "swapping" process, where projects can be swapped in if they do not exceed 110% of the cost of the project being swapped out. One member asked if the committee should pursue an "accumulative swap" to fund the Swannanoa Greenway, while another suggested looking for alternative funding sources such as state commerce funds or federal grants.

The committee also reviewed the Greenway Action Plan, focusing on equity, safety, and specific goals such as developing a transportation equity plan and implementing an etiquette campaign. Staff noted that the GAP plan was originally scheduled to go to Council on May 24, 2022, but may be pushed to June 20 or July 2022 due to pending ADA master plan determinations. Additionally, a representative from Asheville on Bikes discussed their interest in leading a branding and communication plan for greenway etiquette, targeting specific user conflicts. The chair mentioned a grant application from the Blue Ridge Bike Club that might help fund these efforts.

Follow-ups Staff member Lucy agreed to share the transportation equity plan definition with the committee as it is developed, present GAP plan implementation updates regularly on the agenda once adopted, attend the next Southside neighborhood association meeting to introduce draft interpretive signs for the Nasty Branch Greenway, and coordinate with NCDOT on the North Radford Greenway project parameters. Tristan Winkler of the MPO agreed to hold meetings with local delegates and governments in May and June, conduct public engagement over the summer regarding STIP project swaps, bring potential project swaps to the MPO board and committees in August and September, and double-check the total project cost for the Swannanoa River Road project to clarify the swap budget. One committee member offered to send the Blue Ridge Bike Club grant application to staff, and another member representing Asheville on Bikes stated they would send details on their proposed etiquette branding and communication plan.

Impact This meeting highlighted the financial and logistical challenges facing Asheville’s greenway network. The decommitment of the Swannanoa River Road project from the STIP represents a significant setback for the Swannanoa River Greenway, which is currently $2.5 million short of completion. The upcoming summer public engagement on STIP swaps will be a critical opportunity for residents to influence whether the Swannanoa Greenway can be funded through the swap process. Additionally, the potential delay of the Greenway Action Plan to Council until June or July 2022 means that broader strategic goals for equity and safety may take longer to be formally adopted by the City Council.