Environmental and Energy Stewardship Subcommittee Meeting Recap: November 20, 2026
The Buncombe County Environmental and Energy Stewardship Subcommittee convened on November 20, 2026, to review progress on major sustainability infrastructure projects and update its operational schedule. The meeting focused on the construction of the new EMS East facility, the expansion of the county’s electric vehicle (EV) fleet, and the status of battery storage installations across various county properties. Additionally, the subcommittee addressed regional energy resilience, flood mitigation strategies, and regulations regarding data centers and crypto mining.
Key Decisions and Votes The subcommittee took several formal actions during the meeting. A motion to confirm that no members had conflicts of interest was made, seconded, and passed unanimously. Regarding committee composition, a motion was made to recommend a member for a one-year term on the committee; this motion was seconded and passed unanimously. Another member indicated they would step down from the committee, a decision the chair confirmed. Finally, the committee reviewed and accepted proposed dates for 2027, agreeing to continue meeting quarterly on the third Friday.
EMS East Facility and LEED Certification Buncombe County project manager Robert Brown and Eco Impact president Summer Mencho presented an update on the new EMS East facility in Swannanoa. The presentation covered efforts to achieve LEED Gold certification, energy efficiency measures including solar and battery storage, and water conservation. Brown noted the challenge of meeting LEED Gold standards in a rural area, stating, "We are truly trying to completely meet gold [LEED] resolution... It is a lot easier to hit League Gold when you're in metropolitan. We're in an extremely rural, which makes it almost impossible. She [Summer Mencho] is making it possible along with our design team." Mencho highlighted the energy model, stating, "The energy model demonstrates an 83.6% energy cost reduction over a baseline building... That's gonna save over 10,000 [dollars] a year."
During the discussion, a committee member asked how the building’s tight envelope would prevent "sick building" issues. Brown explained that enhanced commissioning, low-VOC materials, and air monitoring systems address these risks, while Mencho added that the commissioning agent is testing the building envelope for air tightness and moisture. Another member raised concerns about water redundancy for resilience. Brown stated that while the facility is currently on the city main, they have capacity for a well and would explore it as an emergency backup for the future EMS West facility, provided it is not used for irrigation to protect the aquifer.
Electric Vehicle and Battery Storage Updates County Fleet Manager Jay Kloot presented an update on the county’s EV strategy, which includes the purchase of pursuit-rated electric vehicles for the Sheriff’s Office and the expansion of charging infrastructure. Kloot stated, "The time is now. We have actually purchased three electric vehicles for our Sheriff's Office... The pursuit rated Chevy Blazer. It is the only pursuit rated electric vehicle available currently." The document provided with the presentation outlines a total fleet of 532 vehicles, with 21 currently electric and 100 hybrid. It also details 15 existing charging locations with 46 ports and 27 planned ports across 8 sites.
A county staff member presented the status of "Project Flourish," a series of battery energy storage system (BESS) installations. The presentation detailed ten projects, including systems at the Family Justice Center, West Asheville Library, Big Ivy Community Center, and others. Most projects were reported as 50% complete, with target completion dates ranging from December 2026 to February 2027. The staff member noted, "We're kind of the tip of the spear on this too... I get a lot of new questions, and I get out of it... I do think it's engaging people in this direction."
Regional Resilience and Regulations The committee discussed the county’s progress relative to the City of Asheville’s energy goals, flood mitigation in the Swannanoa River corridor, and data center regulations. A committee member expressed frustration regarding the lack of recent conversation about physical flood mitigation projects in the Swannanoa corridor, referencing a 2009 joint study. A staff member responded that active work is happening behind the scenes, including the Swannanoa Small Area Plan and discussions on the role of Owen Park in temporary water storage. Another staff member confirmed that the county is joining the Community Rating System at Level 8 and that ordinance changes related to flood and stormwater are being consulted on.
Regarding data centers and crypto mining, a committee member asked if current standards are stringent enough to protect residents from noise and power demands. The chair stated, "I feel like we were on the forefront of this... We have a basic ban on crypto mining in the county and we have fairly stringent standards for data centers... I think that's a worthy conversation to really dig in." The chair suggested a joint conversation with the City of Asheville, which is currently re-evaluating its own moratorium.
Follow-ups and Next Steps Several follow-up actions were identified during the meeting. Robert Brown stated that design work for the EMS West facility has begun, including testing for geothermal feasibility, and that the county will bring this back to the board before commissioning. The chair stated they would brief the full County Commission on the 2009 flood mitigation study and current efforts. Additionally, the chair stated they would request that fire departments participate in the state’s PFAS foam take-back program in the next round of contracts and would send draft language for a local balloon release ban to the commissioners for the next briefing. The committee also agreed to add composting updates and landfill status to future agendas.