Skip to main content
Discussion

Review of Change Order Proposal #003: CE #010 - Gymnasium Chimney Demolition Concealed Conditions

Committee of the Whole Meeting · August 25, 2026 at 8:30 AM

Review of additional concealed/unsuitable building conditions not explicitly captured in the scope of work covered in the RFI responses, and revised drawings. The change request includes steel, masonry, plaster/gypsum board, and paint work for the chimney demolition area. Total amount is $10,046.48 with a 5-day schedule impact. Includes subcontractor proposals from J&K Privette Masonry, Steel Specialty Inc, Gibson Custom Construction, and Turman Commercial Painters.

Documents

Get More From Sunshine Meetings

Bookmarks Notifications Saved Searches