Prime Contract Change Order #004: CE #022 - RFI 15 & 17 Electrical Changes

Committee of the Whole Meeting · August 25, 2026 at 8:30 AM

Approval of Prime Contract Change Order #004 for $6,108.91 and 4 days schedule impact. This change order addresses RFI 15 (Fire Alarm panel relocation/refeeding) and RFI 17 (Basement Electrical Demolition/wiring) for the Gymnasium. Includes subcontractor change order proposal from Lake Electric Co. and associated electrical drawings (E1.0, E1.1, E3.1, E3.2).