Skip to main content
Contract award

Prime Contract Change Order #006: CE #018 - RFI #14: Auditorium - ADA Elevator Access and Ramp

Committee of the Whole Meeting · August 25, 2026 at 8:30 AM

Approval of Prime Contract Change Order #006 for $8,734.97 and 4 days schedule impact. This change order eliminates the wheelchair lift inside the auditorium, increases the size of the exterior ramp, and revises handrails (carbon steel, powder coated black) to meet ADA requirements. Includes approval of ramp design with slope greater than 1:12 by the Inspector.